How to rezone land in Hoover, Alabama
Hoover zones land under a Zoning Ordinance adopted December 21, 2020 and amended through September 28, 2026. A rezoning is a zoning amendment under Section 2.02: the Planning and Zoning Commission holds a hearing and recommends, and the City Council holds its own public hearing and decides. Below are the $100 fee, the 28-day deadline, the notice rules, the limits on continuances and the districts.
New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.
Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.
Who decides a Hoover rezoning?
The City Council. Under Section 2.02.01 of the Zoning Ordinance, a change can be started by the City Council, the Planning Commission or the owners of the property or their authorized agents. Section 2.02.02 says the Planning Commission schedules the hearing at its first regular meeting after notice is complete. After a favorable recommendation, the City Clerk schedules and advertises a public hearing before the City Council as state law requires.
A negative recommendation does not end the case, but the applicant has to ask for the City Council review. The ordinance defines a negative recommendation as a majority of the members present not voting yes on a motion to approve.
What does a Hoover rezoning cost?
$100. Section 2.02.02.A.1 sets a $100.00 fee to cover processing, and the application says it is non-refundable. Section 2.02.02.F adds that the $100.00 administrative fee is due each time the City considers a zoning request, so a request filed again after a denial pays again. A conditional use application is also $100.00 under Section 2.04.01.
Hoover, AL zoning application fees
From the Hoover Zoning Ordinance (Sections 2.02 and 2.04) and the Zoning Amendment Application. Checked Nov. 3, 2026. Checked Nov 9, 2026.
What goes in a Hoover zoning amendment application?
- The owner and applicant names, addresses and phone numbers, with a letter from the owner if the applicant is someone else.
- The address, lot, block and subdivision, and the current and proposed zoning.
- A vicinity map showing the site, the surrounding area and the zoning of the site and adjacent property.
- A legal description of the land to be rezoned.
- Fifteen copies of a scaled site plan, folded to 8.5 by 11 inches, showing rights-of-way, existing and proposed buildings and storm drainage.
- Written statements on the reason for the request, expected traffic and the availability of utilities. Section 2.02.02 also asks how the request relates to the land use pattern nearby.
- File the package with the fee at least 28 calendar days before the meeting. The city's application process page says the deadlines are strictly enforced.
What notice do Hoover neighbors get?
Mailed notice at least 14 days before the Planning Commission hearing. Section 2.02.02.B has the City Clerk mail every owner on the list of adjacent property owners. The notice gives the location by mailing address and legal description, the current and proposed zoning, and the time, date and place of the meeting.
How many times can a Hoover hearing be continued?
Three times at the applicant's request, at each stage. Section 2.02.02 caps continuances at the Planning Commission and again at the City Council. If the City Council denies a rezoning, the Planning Commission will not reconsider the same request for six months.
Which zoning districts does Hoover use?
The city's zoning information page lists these districts:
- Agriculture: A-1.
- Estate and residential: E-1, E-2, R-1, R-2, R-3 (two-family), R-4 (multifamily), R-T-4 (townhouse), R-E (residential equestrian), R-LSF (legacy single-family) and PRD.
- Commercial and industrial: C-P, C-1, C-2, C-3, C-4 and I-1 light industrial.
- Special and planned: MXD mixed use, SPU special use, PDD and the PUD districts PR-1, PR-2, PO, PC and PI.
- Article 14 of the ordinance adds a Highway 280 Overlay District.
How do you look up the zoning on a Hoover parcel?
- Open the Hoover Public Zoning Map. The city notes it is for general information and not for legal, engineering or surveying use.
- Call the Zoning Assistant at 205-444-7517 or email zoning@hooveralabama.gov to confirm a zoning or to place a case on the agenda.
- Our parcel viewer directory and zoning lookup guide cover county records.
Hoover septic and soil review
Hoover sits in Jefferson and Shelby counties, and septic permits go through the county health department for the side your land is on: the Jefferson County Department of Health or the Shelby County Health Department. The state's lot checklist covers sewer and soil questions before you buy.
Hoover planning contacts
- Planning and Zoning Office (Zoning Assistant): 205-444-7517, zoning@hooveralabama.gov.
- Hoover City Hall, 100 Municipal Lane, Hoover, AL 35216. Phone 205-444-7500.
Selling Jefferson County, Alabama land that may need a rezoning
Liberty Acres is an Atlanta-based, family-owned land buyer. We make offers on land as it is zoned today, or on terms that leave time for a rezoning while you keep title until closing. Closing can happen in as little as 14 days. See how rezoning-terms sales work or browse Jefferson County, Alabama land data.
Prefer to sell instead of rezoning yourself? Liberty Acres buys land as-is or on rezoning terms. Local page: sell land in Alabama.
Common questions
What is the rezoning fee in Hoover, AL?
$100, non-refundable, and it is due each time the City considers the request, per Section 2.02.02 of the Zoning Ordinance.
How early do you file a Hoover rezoning?
At least 28 calendar days before the Planning and Zoning Commission meeting, with the fee and all required documents.
What happens after a negative Planning Commission recommendation in Hoover?
The applicant has to ask for City Council review for the case to go forward.
Can you refile a denied Hoover rezoning right away?
No. After a City Council denial, the Planning Commission will not reconsider the same request for six months.