What are land entitlements? Types, process and selling

Land entitlements are the local approvals that decide what can be built on a piece of land. This guide covers each type, who approves it, how the process runs, and what it means if you want to sell land that needs entitlements or land that already has them. Entitlements are one stage of the wider land development process, which runs from feasibility to site work.

Video (1:28): What Are Land Entitlements? Rezoning, Plats and Permits Explained. Watch on YouTube or see our channel.

Key facts

  • Metro Nashville approved 89.3% of the rezoning requests that reached a final result (243 of 272) in Planning Commission agendas from November 2024 to October 2026, per the Liberty Acres Rezoning Approval Tracker.
  • The median Metro Nashville rezoning took 82 days from the Planning Commission to the final Metro Council vote (243 cases).
  • The Metro Nashville Planning Commission recommended approval in 97.7% of the rezoning cases it voted on (292 of 299).
  • Huntsville, Alabama approved 97.8% of the rezoning requests with a final result (45 of 46), and none were denied, with a median of 58 days from the Planning Commission to the final City Council vote.
  • Owner-requested rezonings only in Huntsville (excluding annexation zonings and city-initiated rezonings): 14 of 14 approved, median 58 days, 3 pending.
  • Murfreesboro, Tennessee approved 92.9% of the zoning and rezoning cases its Planning Commission sent to the City Council from January 2025 to March 2026 (26 of 28), with a median of 71 days from the Planning Commission to the final Council vote (26 cases).
  • Franklin, Tennessee (Williamson County) approved 100% of the zoning and rezoning cases with a final result that its Municipal Planning Commission sent to the Board of Mayor and Aldermen from October 2024 to June 2026 (21 of 21), with a median of 61 days from the Planning Commission to the Board's final reading (21 cases).
  • Clarksville, Tennessee (Montgomery County) approved 67.2% of the rezoning cases with a final result that its Regional Planning Commission sent to the City Council from January 2025 to April 2026 (41 of 61), with a median of 37 days from the Planning Commission to the Council's second and final reading for approved cases (41 cases).
  • Metro Nashville's base zone change application fee is $2,050, and a Specific Plan costs $2,900 to $6,100 (Metro Planning fees). Huntsville charges $500 to $800, set by acreage (Rezoning Application).

New research: the Nashville & Huntsville Rezoning Report 2026 shows which rezoning requests pass, which stall after a deferral and how long a decision takes, from 373 recent cases, with free charts and data.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Land entitlements: key points

  • Entitlements are local approvals that decide what can be built on a parcel. They are tied to the land, not the owner.
  • Common types are a rezoning, subdivision plat, site plan, variance, special or conditional use permit, annexation, plan amendment and water and sewer approval.
  • Order matters. Zoning comes first, then utilities, then the plat or site plan. Building permits come last.
  • A simple request can take a few months. A large project with environmental review can take several years.
  • In Metro Nashville, the median rezoning took 82 days from the Planning Commission to the final Council vote. In Huntsville, Alabama, it took 58 days.
  • Entitled land usually sells for more than the same land without approvals, because the buyer skips the approval risk and the wait.
  • You do not have to entitle land before you sell. Many buyers sign contracts that close after the approvals.

What are land entitlements?

Land entitlements are the government approvals a project needs before construction can start. Common examples are a zone change, a variance, a special exception and a site plan review. In most places the planning commission and the city or county council handle zone changes, and a board of zoning appeals or adjustment hears variances and special exceptions.

Some uses are allowed by right and need only a building permit. Other uses need a public hearing and an entitlement first. Your planning office can tell you which group your plan falls in.

Entitlements are tied to the land, not the owner. Zoning sets what the land is allowed to hold, and the other approvals, such as a plat or site plan, carry it out without adding to that allowance.

What are the types of land entitlements?

Entitlement usually combines several approvals. The mix depends on the place and the project. The table below lists the common types, who usually decides each one, and our guide to each.

Types of land entitlements

Who decides varies by place. These are the usual bodies. Checked Nov 16, 2026.

ApprovalWhat it settlesWho usually decidesGuide
RezoningWhich uses and densities the land allowsPlanning commission recommends; council or county commission votesGuide
Subdivision or platHow the land is divided into lots, streets and easementsPlanning commission or planning staffGuide
Site planHow one project sits on the land: buildings, parking, drainage, accessZoning administrator or planning commissionGuide
VarianceRelief from a dimensional rule, such as a setback, because of a hardshipBoard of zoning appeals or adjustmentGuide
Special or conditional use permitWhether a listed use is allowed on this site, with conditionsBoard of zoning appeals, planning commission or councilGuide
AnnexationWhether the land joins a city and its servicesCity councilGuide
Water, sewer and septicWhether utilities can serve the use, or soil can support septicUtility provider or health departmentGuide
Planned unit developmentA custom set of rules for a whole site under one planPlanning commission and councilGuide
Comprehensive plan amendmentWhether the long-range plan supports the usePlanning commissionGuide

What is the difference between entitlements and building permits?

Entitlements decide whether a use and its layout are allowed on the land. Building permits allow construction of a specific building once those approvals are in place.

The planning dictionary Planetizen Planopedia notes that entitlements "cannot be equated with permits." The entitlement is the overall approval to proceed, and permits are separate steps that follow. Read Planetizen's definition.

Some projects are allowed by right. They meet the zoning as written, so they skip discretionary hearings and go straight to permits. Others need a discretionary approval, such as a rezoning or variance, decided at a public hearing.

How does the entitlement process work?

Most entitlement work runs in the same order, and each approval depends on the one before it. A site plan cannot be approved if the zoning does not allow the use, and lots cannot be platted until the utilities can serve them.

How long does land entitlement take?

Land entitlement takes a few months for a simple request and several years for a large project with environmental review. GatherGov's developer guide puts the full range at three months to several years.

Hearing calendars and notice rules set much of the pace. Texas law, for example, requires written notice to owners within 200 feet at least 10 days before the zoning commission hearing on a zoning change, and many places send a request to a planning commission before the council votes.

Local numbers are more useful than national ranges, so ask the planning office for its calendar and recent case times.

For the statewide steps, calendars and fees, start with how to rezone land in Tennessee.

What do land entitlements cost?

Costs come in three layers: application fees, professional fees, and the time the land is tied up. Application fees are published by each city or county, and larger or more discretionary requests, such as a planned development or plan amendment, usually cost more than a standard zone change.

Professional fees for surveyors, engineers and attorneys depend on the project and are not published. Ask for written quotes before you start. See how much it costs to rezone a property and how much it costs to subdivide land.

Budget for impact fees as well as application fees. For help with filings, see when to hire a land use attorney. Build-to-rent sites have their own path: selling land for build-to-rent.

For Nashville projects that need a custom district rather than a standard zone, see how a Nashville Specific Plan (SP) rezoning works.

What can go wrong with entitlements?

Many approvals are discretionary. A planning commission, zoning board or council decides, so the result is never certain. Common problems include:

Two common snags: a buyer's Phase 1 environmental site assessment flags a concern, or neighbors challenge a small rezoning as spot zoning.

  • Denial, or a smaller approval than requested, often after neighbor opposition at a public hearing.
  • Conditions that add cost, such as road improvements, buffers or design limits.
  • No sewer capacity or no public sewer nearby, which can limit the number of lots.
  • Missed filing deadlines, which push the case to a later hearing.
  • Approvals that expire. Many special exceptions, site plans and preliminary plats lapse if permits are not pulled within a set time.

How do entitlements change land value?

Entitled land already has the approvals a builder needs, and raw land has none of them. A builder who buys entitled land carries less approval risk and can start sooner, so entitled land usually sells for more than the same land without approvals.

We do not publish a percentage, because the gap depends on the market, the approved use and the cost of the work. To see the gap in your area, compare recent sale prices of approved lots with raw acreage nearby in the county's sales records. Our guides to how to value vacant land and whether land is worth more if rezoned show how.

For how a developer works out a land price, see how much your land is worth to a developer.

For what studies and appraisal rules say, read does rezoning increase land value?.

Short answer on value: does rezoning raise land value? Usually, when the new use is in demand, and less before approval than after.

How a builder or developer funds the price, through lot takedowns, joint ventures or A&D loans, is covered in builder takedowns, JVs and A&D loans.

Entitled land vs land without entitlements

General patterns. Local rules and each contract decide the details. Checked Nov 16, 2026.

QuestionLand without entitlementsEntitled landSource
What can be builtOnly what the current zoning allows by rightThe use, density and layout in the approvalsSource
How it usually sellsOften on an option or contingent contract that closes after approvalAs a standard sale priced on the approved useSource
What a buyer pays forToday's use, less the risk, cost and wait of approvalsThe approved use, with those risks removedSource
Time before constructionA few months to several years of hearings and studiesPermits and site work can start soonerSource
Main riskDenial, conditions that add cost, or no utility capacityApprovals that expire if work does not start in timeGuide

Should you sell land before or after entitlement?

Selling before entitlement is simpler. You avoid the fees, the studies and the chance of denial, and the buyer takes on the approval risk. Selling after entitlement can bring a higher price, but you pay for the work up front and wait through the hearings.

A middle path is a sale with terms that allow time for approvals. The buyer does the entitlement work while you still own the land, and closing comes after the approvals. An option agreement gives a buyer the right, but not the duty, to buy at a set price within a set time. Cornell's Legal Information Institute explains that the seller cannot revoke the offer during the option period. A contingent purchase contract binds both sides from signing, and the condition only delays the duty to close.

If you tie up land during entitlement, put these points in writing: a price that reflects the approved use, deposits or option payments and when they become nonrefundable, an outside closing date with limits on extensions, which approvals must come through and who pays for studies, and copies of surveys and plans if the deal ends. Have a real estate attorney read the contract before you sign.

We also buy land that still needs a zone change in places such as Robertson County, Tennessee and Limestone County, Alabama.

Many developers hold land with an option while they work on approvals. See land option agreements for the fee, term and what you give up.

How does Liberty Acres buy land that needs entitlements?

Liberty Acres is a family-owned land company based in Atlanta, Georgia. We buy land anywhere in the US, in any condition, including land that still needs approvals. On rezoning-terms deals, we handle the rezoning work and pay for it. For larger parcels with development potential, we can sign terms that allow time for zoning and entitlement work. You keep title until closing, closing comes later, and the price can reflect the value that work adds.

We pay back taxes and all closing costs, with no agents and no commissions, and we close through a title company, escrow company or real estate attorney. Read how we buy land that needs rezoning, selling land you could subdivide, or get an offer. Already have approvals in place? Read how to sell entitled land.

To compare homebuilders, developers, land development companies and land buyers, see who buys land that needs entitlements.

To start, see how selling land to Liberty Acres works.

How do land entitlements work in Tennessee and Alabama?

Nashville and Huntsville show how the same approvals are handled locally.

Tennessee: in Metro Nashville, the Planning Commission and Metro Council handle a zone change, and the Board of Zoning Appeals hears variances and special exceptions. Metro's subdivision rules say the regulations "provide for the division of land under the existing zoning entitlements." A standard zone change is $2,050, a Specific Plan rezoning runs $2,900 to $6,100 by project size, a subdivision concept plan is $3,000 and a major community plan amendment is $9,150. Nashville's special exception packet says an approved applicant has two years to obtain the permit or must refile, and Metro Planning takes a pre-application inquiry form.

Alabama: Huntsville requires a pre-meeting before a subdivision and says the subdivision process takes about 120 days from start to finish when there are no obstacles. Its 2026 rezoning schedule sends each request to the Zoning Committee, then the Planning Commission, then the City Council.

Our local guides list the official fees and deciders with links: Nashville, Williamson County, Rutherford County, Wilson County, Sumner County, Huntsville and Limestone County. The Rezoning Approval Tracker shows recent Nashville and Huntsville rezoning cases and how long each took.

Check with your local planning, zoning or health office before you rely on any of this. This is general information, not legal advice.

In Tennessee, rezoning is a local process. For the steps, who votes, and a directory of city and county guides, see how to rezone land in Tennessee.

Entitlement guides, step by step

Each guide below covers one step or approval in detail, with official sources.

Common questions

What is the entitlement process in real estate?

It is the series of local approvals a site needs before anyone can build on it. It usually starts with a zoning check, then any rezoning, variance or special use, then a subdivision plat and site plan, and finally permits. Some steps need public hearings. In Nashville, rezoning cases reached a final Council vote in a median of 82 days on our rezoning approval tracker.

What is the difference between approvals and entitlements?

Entitlements are the land use approvals that set what may be built, such as zoning, rezoning, variances, plats and site plans. Approvals is the wider word. It also covers the building permits and utility sign-offs that come after the entitlements are in place.

What is the difference between entitlements and permits?

Entitlements decide what may be built on the land, such as the zoning, plat or site plan. Building permits come after and allow construction of a specific building.

What does by-right development mean?

A by-right project meets the zoning as written. It needs staff review and building permits, with no discretionary hearing.

Do entitlements transfer when land is sold?

Usually yes. Entitlements are tied to the land, not the owner. Check whether any approval has an expiration date or conditions a new owner must meet.

What is land entitlement?

Land entitlement is the process of getting the government approvals that give a property the legal right to be developed for a specific use. Entitlements can include a rezoning, subdivision plat, site plan, variance, use permit and utility sign-offs. Entitled land usually sells for more because the buyer skips the approval risk and the wait. In our case data, the median rezoning took 82 days from the Planning Commission to the final vote in Metro Nashville (243 cases) and 58 days in Huntsville, Alabama (45 approved cases), per the Liberty Acres Rezoning Approval Tracker.

What are land entitlements?

They are the government approvals needed before a project can be built on a parcel. They can include zoning, subdivision, site plan, variance, use permit, annexation and utility approvals.

What is entitled land?

Entitled land has the approvals a builder needs for a planned use, such as the right zoning, an approved plat or site plan, and utility capacity. Raw land does not, so the buyer takes on that work and risk.

How long does land entitlement take?

A simple request can take a few months. A large project with environmental review can take several years. Hearing calendars and notice rules set much of the pace.

Are rezoning and entitlement the same thing?

No. Rezoning is one type of entitlement. Entitlement also covers subdivision plats, site plans, variances, use permits, annexation, plan amendments and utility approvals.

Do I have to entitle my land before I sell?

No. You can sell as-is and let the buyer handle approvals, or sign terms that allow time for the buyer to do the entitlement work before closing.

Is a rezone-contingent contract binding on the seller?

Usually yes, from the day it is signed. The buyer's duty to close waits on the approval, and the seller usually cannot sell to someone else meanwhile. Have an attorney read the terms.

What is a plat in the entitlements process?

A plat is the surveyed map of lots, streets and easements used in a lot split or subdivision. It usually needs planning approval before new lots can be sold. See the glossary.