Nashville & Huntsville Rezoning Report 2026
November 2026 update: Middle Tennessee and North Alabama
An original study of 373 rezoning cases in Metro Nashville-Davidson County and Huntsville, Alabama, built from Planning Commission agendas and City Council records, with U.S. Census Bureau building permit data for context. It shows which requests pass, which stall, and how long a decision takes. Liberty Acres is an Atlanta-based, family-owned land company that buys land in both markets.
Key findings, November 2026
- 87.9% of rezoning requests with a final result were approved across five cities: Nashville, Franklin, Murfreesboro, Clarksville and Huntsville (376 of 428 decided cases).
- Clarksville is the outlier. Its City Council approved 67.2% of decided rezonings (41 of 61) and voted down 20, including 12 the Regional Planning Commission had recommended for approval.
- Nashville almost never votes a rezoning down. None of 272 decided Metro cases failed on a Council vote; the 29 that did not pass were deferred indefinitely (18), withdrawn (8) or stopped at the Planning Commission (3).
- A Planning Commission deferral is the clearest warning sign in Nashville: cases never deferred passed 95.1% of the time (175 of 184), against 77.3% for cases deferred at least once (68 of 88).
- Speed varies more than approval. The median approved case took 37 days from Planning Commission to final vote in Clarksville (41 cases) and 82 days in Nashville-Davidson County (243 cases).
Cite as: Liberty Acres, Nashville & Huntsville Rezoning Report 2026 (November 2026 update), libertyacres.land/guides/nashville-huntsville-rezoning-report-2026. Free to reuse under CC BY 4.0.
November 2026 update: five cities
This edition adds Franklin, Murfreesboro and Clarksville from the Rezoning Approval Tracker and updates Nashville's pending bills through the November 5, 2026 Metro Council meeting, where 2 more rezonings were approved. 23 Nashville rezoning bills are still pending at the Council (14 awaiting third reading, 9 awaiting a public hearing).
| City | Cases | Approved, of decided | Not approved | Pending | Median days to final vote | Agendas covered |
|---|---|---|---|---|---|---|
| Nashville-Davidson County, TN | 324 | 89.3% (243 of 272) | 29 | 52 | 82 (243 cases) | Nov 2024 to Oct 2026 |
| Franklin, TN | 22 | 100% (21 of 21) | 0 | 1 | 61 (21 cases) | Oct 2024 to Jun 2026 |
| Murfreesboro, TN | 28 | 92.9% (26 of 28) | 2 | 0 | 71 (26 cases) | Dec 2024 to Feb 2026 |
| Clarksville, TN | 64 | 67.2% (41 of 61) | 20 | 3 | 37 (41 cases) | Jan 2025 to Apr 2026 |
| Huntsville, AL | 49 | 97.8% (45 of 46) | 1 | 3 | 58 (45 cases) | Nov 2024 to Oct 2026 |
| All five | 487 | 87.9% (376 of 428) | 52 | 59 |
Median days run from the Planning Commission's final action to the final vote of the Nashville-Davidson County Metro Council, Franklin Board of Mayor and Aldermen, Murfreesboro City Council, Clarksville City Council, Huntsville City Council, approved cases only. Cities cover different date ranges, so compare rates with their sample sizes. Franklin cases · Murfreesboro cases · Clarksville cases
Why requests fail: what the public record shows
Minutes and agendas record how a request ended far more often than why. Here is how the 52 decided requests that did not pass ended:
| City | How it ended | Cases |
|---|---|---|
| Nashville | Deferred indefinitely | 18 |
| Nashville | Withdrawn | 8 |
| Nashville | Planning Commission disapproval, no Council bill | 3 |
| Nashville | Voted down by the Metro Council | 0 |
| Clarksville | Voted down by the City Council | 20 |
| Murfreesboro | Deferred indefinitely | 1 |
| Murfreesboro | Denied after the companion annexation failed | 1 |
| Huntsville | Withdrawn | 1 |
| Franklin | None (every decided case approved) | 0 |
- Clarksville. The City Council followed a Planning Commission approval recommendation 76.5% of the time (39 of 51) and approved 1 of 9 requests the Commission recommended against. 18 of 20 denials came on first reading, 2 on second.
- Nashville. Requests in trouble tend to be deferred again and again, then deferred indefinitely or withdrawn, rather than voted down. Multifamily (RM) requests had the lowest approval rate of any zoning family (see below).
- Murfreesboro. The one denial came when the Council failed the companion annexation resolution, so the zoning ordinance never reached a vote. Council deferrals in the minutes cite issues such as drainage.
- Huntsville and Franklin. No council denials in the window. Huntsville's one non-approval was a withdrawal.
Headline findings
- Nashville approved 89.3% of rezoning requests that reached a final result. 243 of 272 decided cases were approved. No rezoning bill in the set failed on a Metro Council floor vote. Requests that did not pass ended another way: 18 were deferred indefinitely, 8 were withdrawn and 3 stopped after a Planning Commission disapproval with no Council bill.
- A Planning Commission deferral is the clearest warning sign. Cases the Commission never deferred were approved 95.1% of the time (175 of 184). Cases deferred at least once were approved 77.3% of the time (68 of 88), and 70.6% after three or more deferrals. For approved cases, the median from first agenda to final vote was 131 days with a deferral and 82 days without one.
- Specific Plans get deferred far more often, then pass at about the same rate. 55.6% of new Specific Plan (SP) requests were deferred at least once at the Planning Commission, against 11% of base zone changes. Approval rates ended up close: 90.3% for new SPs and 89.2% for base zone changes.
- Multifamily requests fail most often in Nashville. Requests for a multifamily (RM) district were approved 76% of the time (19 of 25), the lowest of any zoning family with at least 5 decided cases. Mixed use and office requests were approved 96.8% of the time (30 of 31).
- Huntsville decides faster, on much bigger tracts. Huntsville's median was 58 days from the Planning Commission to the final Council vote, against 82 days in Nashville. The median approved Huntsville tract was 19.35 acres, against 1.04 acres in Nashville. 61.2% of Huntsville's cases (30 of 49) zoned land newly annexed into the city. Huntsville approved 45 of 46 decided cases and denied none.
- Two council districts carry a quarter of Nashville's rezoning load. District 16 (43 cases) and District 2 (36 cases) together account for 24.4% of the 324 Nashville cases. 33 of Metro's 35 council districts had at least one case.
- Nashville is not getting faster. Across 8 quarters with at least 10 approved cases (2025 Q1 to 2026 Q4), the quarterly median from Planning Commission to final vote stayed between 68 and 89 days.
- Nashville homebuilding permits keep falling while Madison County holds. Davidson County authorized 5,632 housing units in 2025, 65.5% below its 2021 peak of 16,310, and January to September 2026 ran 26.2% below the same months of 2025. Madison County, Alabama, home to Huntsville, authorized 2,866 single-family homes in 2025 with about 58% of Davidson's population, against 2,739 in Davidson.
Free to reuse under CC BY 4.0. Download the summary CSV · building permits CSV · Nashville cases · Huntsville cases
Nashville vs Huntsville at a glance
| Measure | Nashville-Davidson County | Huntsville |
|---|---|---|
| Cases tracked | 324 | 49 |
| Approved, of cases with a final result | 89.3% (243 of 272) | 97.8% (45 of 46) |
| Denied or failed on a Council vote | 0 | 0 |
| Median days, Planning Commission to final vote | 82 (range 19 to 495) | 58 (range 30 to 72) |
| Approved cases decided within 60 days | 10.7% (26 of 243) | 55.6% (25 of 45) |
| Median approved tract | 1.04 acres | 19.35 acres |
| Deferred at least once by the Planning Commission | 30.6% (99 of 324) | Not tracked |
| Housing units permitted, 2025 (county) | 5,632 in Davidson | 4,070 in Madison |
| Units permitted per 1,000 residents, 2025 | 7.6 | 9.4 |
| Single-family units per 1,000 residents, 2025 | 3.7 | 6.6 |
| Units permitted, Jan. to Sep. 2026 vs 2025 | 3,162 vs 4,282 (-26.2%) | 2,761 vs 2,840 (-2.8%) |
Rezoning figures cover each city's own cases. Permit figures are county totals (Davidson County is the consolidated Metro government; Huntsville sits mainly in Madison County and extends into Limestone County).
The data in charts
Each chart is built from the same data as the tables and can be downloaded as an SVG or PNG file or embedded with the code under it. Reuse with credit to Liberty Acres under CC BY 4.0.
Franklin approved every decided case (21 of 21). Murfreesboro approved 26 of 28. Smaller samples move more on one or two votes.
Clarksville's approved cases ranged from 9 to 100 days. Nashville-Davidson County's ranged from 19 to 495 days; Metro Council rezoning bills take three readings, with the public hearing at second reading.
Outside Clarksville, only 1 decided case in the other four cities ended in a losing council vote. In Clarksville, 18 of the 20 denials came on first reading.
11 of Clarksville's 20 Council denials had a staff recommendation of approval. 3 cases have no final result in the posted minutes and are left out.
Huntsville approved at least 96.7% of decided cases in both of its main case types. In Nashville, base zone changes, new SPs and SP amendments all landed within a few points of each other. Urban Design Overlay cases are too few (6 decided) to chart.
99 of 324 Nashville cases (30.6%) were deferred at least once at the Planning Commission. Deferral also adds time: approved cases that were deferred took a median of 131 days from first agenda to final vote (68 cases), against 82 days for those never deferred (175 cases).
Of the 25 decided multifamily (RM) requests, 6 were not approved: 5 deferred indefinitely, 1 stopped after a Planning Commission disapproval.
Huntsville's quarterly medians are based on smaller counts (shown in the CSV) and sit below Nashville's in every quarter where both have cases.
District numbers are Metro Council districts as listed on the Planning Commission agendas.
Davidson County's 2021 peak was driven by buildings with 5 or more units. Madison County's totals are mostly single-family homes.
Approval by type of zoning change
| Market and type | Cases | Approved | Rate | Median days |
|---|---|---|---|---|
| Nashville: Base zone change | 182 | 132 of 148 | 89.2% | 82 |
| Nashville: New Specific Plan (SP) | 108 | 84 of 93 | 90.3% | 82 |
| Nashville: Specific Plan amendment | 27 | 23 of 25 | 92% | 82 |
| Nashville: Urban Design Overlay | 7 | 4 of 6 | 66.7% | 51 |
| Huntsville: Zoning newly annexed land | 30 | 29 of 30 | 96.7% | 58 |
| Huntsville: Rezoning land already in a city district | 17 | 14 of 14 | 100% | 58 |
Which rezoning requests fail most in Nashville
Grouped by the zoning district requested. Not approved means deferred indefinitely, withdrawn or stopped after a Planning Commission disapproval.
| Requested zoning | Decided | Approved | Rate | Not approved |
|---|---|---|---|---|
| Multifamily (RM) | 25 | 19 | 76% | 6 |
| Commercial (CS, CL) | 5 | 4 | 80% | 1 |
| Single-family (RS, AR) | 8 | 7 | 87.5% | 1 |
| Industrial (IWD, IR, IG) | 9 | 8 | 88.9% | 1 |
| Specific Plan (new or amended) | 118 | 107 | 90.7% | 11 |
| One and two-family (R) | 69 | 63 | 91.3% | 6 |
| Mixed use and office (MU, OR) | 31 | 30 | 96.8% | 1 |
By tract size, the approval rate was 90% for under 1 acre (117 of 130), 91.1% for 1 to 5 acres (51 of 56), 85.2% for 5 to 20 acres (46 of 54) and 90% for 20 acres or more (27 of 30).
Deferral rates
| Planning Commission deferrals | Cases | Approved | Rate | Deferred indefinitely |
|---|---|---|---|---|
| Never deferred | 225 | 175 of 184 | 95.1% | 4 |
| Deferred at least once | 99 | 68 of 88 | 77.3% | 14 |
| Deferred three or more times | 37 | 24 of 34 | 70.6% | 8 |
Deferral rate by quarter of the Planning Commission's final action:
| Quarter | Cases | Deferred at least once | Share |
|---|---|---|---|
| 2024 Q4 | 23 | 3 | 13% |
| 2025 Q1 | 40 | 14 | 35% |
| 2025 Q2 | 58 | 23 | 39.7% |
| 2025 Q3 | 32 | 10 | 31.3% |
| 2025 Q4 | 33 | 7 | 21.2% |
| 2026 Q1 | 34 | 6 | 17.6% |
| 2026 Q2 | 33 | 10 | 30.3% |
| 2026 Q3 | 42 | 7 | 16.7% |
| 2026 Q4 | 10 | 1 | 10% |
Approval by Metro Council district
Districts with at least 10 cases. Every district is in the CSV.
| District | Cases | Approved | Rate | Median days |
|---|---|---|---|---|
| District 16 | 43 | 35 of 37 | 94.6% | 82 |
| District 2 | 36 | 31 of 33 | 93.9% | 82 |
| District 5 | 28 | 17 of 19 | 89.5% | 82 |
| District 1 | 25 | 12 of 15 | 80% | 110 |
| District 21 | 18 | 13 of 14 | 92.9% | 82 |
| District 17 | 15 | 14 of 14 | 100% | 82 |
| District 8 | 14 | 11 of 11 | 100% | 110 |
| District 9 | 14 | 12 of 14 | 85.7% | 89 |
| District 19 | 14 | 12 of 14 | 85.7% | 68 |
| District 7 | 10 | 9 of 10 | 90% | 82 |
| District 32 | 10 | 6 of 9 | 66.7% | 55 |
| District 33 | 10 | 5 of 7 | 71.4% | 96 |
Time to decision by quarter
| Quarter of final vote | Nashville median days | Nashville cases | Huntsville median days | Huntsville cases |
|---|---|---|---|---|
| 2024 Q4 | 33 | 2 | 0 | |
| 2025 Q1 | 82 | 23 | 65 | 5 |
| 2025 Q2 | 82 | 27 | 58 | 5 |
| 2025 Q3 | 89 | 51 | 65 | 8 |
| 2025 Q4 | 82 | 26 | 37 | 4 |
| 2026 Q1 | 89 | 38 | 65 | 7 |
| 2026 Q2 | 68 | 21 | 58 | 5 |
| 2026 Q3 | 82 | 39 | 58 | 7 |
| 2026 Q4 | 76 | 16 | 58 | 4 |
Quarters with few cases, including the partial current quarter, swing on a handful of votes. Read them with the counts.
Editions
- November 2026 (updated November 10, 2026): adds Franklin, Murfreesboro and Clarksville; Nashville pending bills checked in Legistar through the November 5, 2026 Council meeting; how not-approved requests ended; embeddable charts.
- First edition (November 3, 2026): Nashville and Huntsville rezoning outcomes, deferrals, timelines and building permits.
The report is updated monthly on this page.
Methodology
- Nashville cases. Every zone change (Z), Specific Plan (SP) and Urban Design Overlay (UD) case on the posted Metro Planning Commission action agendas from November 14, 2024 to October 22, 2026, matched to its Metro Council bill through the public Legistar API. Building-material companion bills are excluded. This is the same data as the Rezoning Approval Tracker.
- Franklin, Murfreesboro and Clarksville cases. Zoning and rezoning cases from Planning Commission minutes followed to the final vote of the Franklin Board of Mayor and Aldermen (Oct 2024 to Jun 2026 agendas), the Murfreesboro City Council (Dec 2024 to Feb 2026) and the Clarksville City Council (Jan 2025 to Apr 2026), as listed in the Rezoning Approval Tracker. Clarksville recommendations are as printed in the Council minutes; 3 Clarksville cases with no final result in posted minutes are left out of rates.
- Huntsville cases. Every zoning and rezoning case on Huntsville Planning Commission agendas from November 19, 2024 to October 27, 2026, followed to the City Council's final action in Legistar.
- Approval rate. Approved cases divided by cases with a final result (approved, denied, withdrawn or deferred indefinitely). Pending cases are left out of rates.
- Days to decision. Calendar days from the Planning Commission's final action to the Council's final vote, approved cases only. Medians of an even count are rounded to the nearest day.
- Deferrals. The number of times a case was deferred at the Planning Commission, read from the action agendas. Council deferrals are tracked separately in the case CSV.
- Requested zoning. Nashville cases grouped by the family of the district requested, per Metro's zoning classifications. Groups with fewer than 5 decided cases are not shown, and Urban Design Overlays appear only under type of change because they are overlays, not base districts.
- Quarters. Time to decision is grouped by the quarter of the final Council vote. Deferral rates are grouped by the quarter of the Planning Commission's final action.
- Building permits. Housing units authorized in new privately owned residential buildings, from the U.S. Census Bureau Building Permits Survey county files (annual 2019 to 2025, and year-to-date through September for 2025 and 2026), per 1,000 residents using the Vintage 2025 county population estimates. Retrieved November 3, 2026.
Limits
- Three Nashville Planning Commission action agendas in the window were not posted, so cases heard only on those dates may be missing.
- 24 Nashville cases have a Planning Commission action but no Council bill found in Legistar yet. They count as pending.
- Groups with few cases (for example Urban Design Overlays, single districts or recent quarters) can move several points on one or two votes.
- Franklin (21 decided), Murfreesboro (28) and Clarksville (61) are small samples with different date ranges from Nashville and Huntsville.
- Public records rarely state why a council voted a request down, so the report groups not-approved cases by how they ended, not by reason.
- Huntsville denied no rezoning in the window, so the study cannot say which Huntsville requests fail most. Huntsville deferrals were not tracked.
- The study shows patterns, not causes. A deferral often signals open issues with neighbors, staff or design, and those issues, not the deferral itself, may drive the outcome.
- Census permit counts are estimates that include imputation for non-reporting places, and they cover whole counties rather than city limits.
- The report covers totals and groups only and does not single out any property, owner or applicant.
Reuse and citation
The data, tables and charts are licensed Creative Commons Attribution 4.0 (CC BY 4.0). Reuse them in any medium with credit and a link: Source: Liberty Acres, Nashville & Huntsville Rezoning Report 2026, libertyacres.land/guides/nashville-huntsville-rezoning-report-2026. Reporters with questions about the data can reach Spencer Cox through the author page.
Questions about the report
What share of rezoning requests get approved in Nashville?
89.3% of Metro Nashville rezoning cases with a final result were approved (243 of 272), based on Planning Commission action agendas from November 14, 2024 to October 22, 2026 matched to Metro Council bills.
How long does a rezoning take in Nashville compared with Huntsville?
The median approved case took 82 days from the Planning Commission's final action to the final Council vote in Nashville and 58 days in Huntsville. Add the filing and staff review period before the first Commission hearing.
Which rezoning requests fail most often in Nashville?
Requests for a multifamily (RM) district had the lowest approval rate, 76% (19 of 25). Cases the Planning Commission deferred at least once were approved 77.3% of the time, against 95.1% for cases never deferred.
Which Middle Tennessee city denies the most rezonings?
Clarksville. Its City Council approved 67.2% of rezoning cases with a final result (41 of 61) and voted down 20, 18 of them on first reading. Franklin approved 100% (21 of 21), Murfreesboro 92.9% (26 of 28) and Nashville 89.3% (243 of 272).
How often is this report updated?
Monthly. Each edition is added to this page with its date, and the case files behind it are in the Rezoning Approval Tracker. This is the November 2026 edition, updated November 10, 2026.
Can I reuse these numbers and charts?
Yes. The data, tables and charts are licensed CC BY 4.0. Credit "Liberty Acres, Nashville & Huntsville Rezoning Report 2026" with a link to this page.
Own land in Nashville or Huntsville?
We are an Atlanta-based, family-owned land company. We buy land as it is, including land that needs rezoning, and we handle the entitlement work ourselves. Closing can happen in as little as 14 days. See how we buy land that needs rezoning.
Get an offer on your landSources
- Metro Nashville Planning Commission: meeting documents and action agendas
- Metro Nashville Council legislation (Legistar)
- Legistar public web API for Metro Nashville matters
- City of Huntsville: Planning Commission agendas and minutes
- Franklin, Murfreesboro and Clarksville case files, with links to each city's minutes (Rezoning Approval Tracker)
- Huntsville City Council legislation (Legistar)
- U.S. Census Bureau Building Permits Survey: county files
- U.S. Census Bureau: Vintage 2025 county population estimates