Preliminary plat vs final plat: what each one does

A subdivision is approved twice. First the layout, then the surveyed map that becomes public record. Knowing which stage you are in tells you what can still change, what can expire and when lots can be sold. This guide is part of our land entitlements guide.

What is a preliminary plat?

A preliminary plat is the planning-level drawing of a proposed subdivision. It shows the street layout, lot lines, open space, dedications and major site changes. It is reviewed before anyone pays for full engineering.

Metro Nashville calls this stage the concept plan. Its rules describe it as a master plan of the subdivision that shows street, lot and open space layouts, dedications and environmental changes. It must include site conditions and off-site conditions at least 300 feet beyond the boundary.

What is a final plat?

A final plat is the precise, surveyed map of the lots, streets and easements, sealed by a licensed surveyor. Once signed by the planning commission or its secretary, it is recorded with the register of deeds or probate office. Recording is what makes the lots legal parcels.

Approval of a plat is not acceptance of the streets. Alabama law says plat approval does not mean the public accepts any street or open space shown on it. Streets are accepted separately, after they are built to standard.

Preliminary plat vs final plat at a glance

The table compares the two stages. Local regulations decide the exact contents and approvals.

Preliminary plat vs final plat

Typical contents and approvals. Metro Nashville rules used as the example where noted.

Preliminary plat or concept planFinal plat
PurposeApprove the layout before engineeringCreate legal lots of record
ShowsStreets, lots, open space, dedications, site conditionsSurveyed lot lines, bearings, easements, certificates
Prepared byEngineer or planner, with a surveyorLicensed surveyor
Approved byPlanning commissionPlanning commission or its secretary
Comes afterPre-application meeting and feasibilityConstruction plans, plus built or bonded improvements
RecordedNoYes, with the county
Lasts (Nashville)4 years to final plat recordingMust record within 1 year

What happens between the preliminary and final plat?

Engineering and construction. After the layout is approved, engineers prepare construction plans for roads, sidewalks, drainage, water, sewer, utilities and landscaping. Agencies review them.

Then the improvements are built, or the developer posts a performance bond. Metro Nashville lets the commission require improvements before the plat is signed. Otherwise the bond must be approved first, in an amount set from each agency's recommendation.

How long does the planning commission have to decide?

Many states set a deadline and treat silence as approval. In Tennessee, a plat goes on the agenda within 30 days of filing, and the commission must act within 60 days after it first considers it. In Alabama, a municipal planning commission must act within 30 days of submission, after a hearing with notice to adjoining owners.

Texas requires action within 30 days after filing. If the plat is approved with conditions, the applicant's response must be decided within 15 days. In each state, the applicant can waive the deadline, and asking for a deferral is often treated as a waiver.

How long does a preliminary or final plat approval last?

Set by local rules, plus state vesting laws. In Metro Nashville, a concept plan approval lasts four years to the recording of the final plat, with possible one-year extensions. An approved final plat expires if it is not recorded within one year. A phased concept plan stops expiring once one phase is recorded with its improvements secured.

Tennessee's Vested Property Rights Act locks the development standards for three years from submission of a preliminary development plan. Final approval, permits and site work in that time add two more years. The total is capped at ten years unless the local government extends it.

Can you sell lots before the final plat is recorded?

Usually not as separate lots. Most states bar selling a lot in a new subdivision until the plat is approved and recorded. You can still sell the whole parcel at any stage. A buyer will look closely at what is approved, what is bonded and what can still expire.

Liberty Acres buys land at every stage, from raw acreage to land with an approved concept plan. See sell entitled land or land that needs entitlements.

How do plats work in Tennessee and Alabama?

Tennessee: Metro Nashville's final plat fee is $1,375, and a major subdivision concept plan is $3,000. Nashville gives notice of plat hearings to owners within 300 feet. Its staff may sign a final plat of up to five lots, or up to 25 lots after an approved concept plan. See subdividing land in Nashville.

Alabama: every plat before a municipal planning commission gets a hearing. Notice goes by certified mail to the applicant and adjoining owners at least five days before. Under Alabama case law, the 30-day clock runs from the hearing. See subdividing land in Huntsville.

Common questions

Is a concept plan the same as a preliminary plat?

They do the same job. Metro Nashville uses the term concept plan for the layout approval that comes before construction plans and the final plat. Other places call it a preliminary plat or sketch plan.

Do all subdivisions need a preliminary plat?

No. Small splits on an existing road usually go straight to a final plat. In Nashville, a minor subdivision may begin with a final plat and a concept plan is optional.

What happens if the planning commission does not act on a plat in time?

In Tennessee, Alabama and Texas, the plat is treated as approved if the commission misses the state deadline, unless the applicant agreed to an extension.

What is a plat?

A plat is a scaled map of land divided into lots, showing boundaries, streets and easements. See our guide to land surveys and plats for how to read one.

What is a replat?

A replat redraws a recorded plat to move, combine or split lots. See lot line adjustment vs replat.