How to rezone land in Mobile, Alabama

Mobile rezones land under Article 5 of its Unified Development Code, amended June 3, 2025. A rezoning is a zoning map amendment under Section 64-5-5: the Planning Commission holds a hearing and recommends, and the City Council holds its own hearing and decides. Below are the $500 fee, the pre-application and neighborhood meetings, the notice rules, the approval criteria and the districts.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

Who has the final say on a Mobile map amendment?

The City Council. Under Section 64-5-5.B of the Unified Development Code, a rezoning can be started by the City Council, the Planning Commission, or the owner or an agent filing with the Director. The Director sends a complete application to the Planning Commission within 45 days. The Commission files its recommendation within 15 days of its decision, and the City Council schedules a hearing within 30 days and approves, approves with conditions, or denies.

Conditions attached to an approval run with the land and are recorded in Mobile County Probate Court. Section 64-5-5.G allows an appeal to Mobile County Circuit Court within 42 days of the decision.

    How much does a Mobile map amendment cost?

    $500. The Planning Commission Application, revised March 2025, sets $500 for a rezoning, text amendment or specific area plan. The applicant also pays first-class postage for every notified owner within 300 feet, a legal ad fee after the Planning Commission and before the City Council hearing, and the cost of recording approved documents in Probate Court.

      Mobile, AL Planning Commission fees

      From the Build Mobile Planning Commission Application, revised March 2025. Postage, legal ad and recording costs vary and are billed to the applicant. Checked Nov. 3, 2026. Checked Nov 9, 2026.

      WhereApplicationFeeSource
      MobileRezoning, text amendment or specific area plan$500Source
      MobileConditional use permit$500Source
      MobilePlanned development$500Source
      MobileMailed notice to owners within 300 feetFirst-class postage per ownerSource

      Which meetings come before a Mobile filing?

      • A pre-application meeting with staff under Section 64-5-3. When a neighborhood meeting is required, it must come at least 14 days before that meeting. Otherwise it must fall within 180 days before you file.
      • A neighborhood meeting under Section 64-5-4 when the request is for a higher classification. It must be held on a weekday between 5 p.m. and 8 p.m., last at least one hour, take place in a public or institutional building, and fall no more than 60 days before the Planning Commission hearing.
      • If the neighborhood meeting comes after filing, it must be at least 21 days before the hearing. Documentation of the meeting is due 15 days before the hearing.

      What goes in a Mobile rezoning application?

      • The Planning Commission Application with Checklist B, filed by noon on the deadline. Hard-copy filings need seven copies.
      • A boundary plan of the property and, where needed, a concept or site plan.
      • Mailing labels for every owner within 300 feet, taken from Revenue Commissioner records and verified through Probate Court.
      • Neighborhood meeting documentation, and a traffic study if the Traffic Engineer requires one.
      • A justification statement covering consistency with the Map for Mobile future land use map, any mistake in the current zoning, changed conditions and the effect on public welfare.

      How are Mobile neighbors notified?

      Table 64-5-5.1 sets three kinds of notice. Owners abutting or within 300 feet get mailed notice 15 days before the Planning Commission hearing and again 15 days before the City Council hearing. A sign goes on the property 15 days before the Planning Commission hearing. The Council hearing is published 15 days before, or for three consecutive weeks, under Code of Alabama Section 11-52-77.

      Section 64-5-5.D allows one holdover. A withdrawal after notice has gone out bars the same request for six months.

        What does Mobile weigh in a rezoning?

        Section 64-5-5.E lists the approval criteria: consistency with the comprehensive plan, a mistake in the original zoning, compatibility with nearby uses, public health and safety, the capacity of streets and utilities, and changed conditions in the area. Under Section 64-5-5.F, a Planning Commission recommendation to deny, a City Council denial or a withdrawal after notice bars a new request for six months.

          What districts does the Mobile UDC set up?

          Section 64-2-1 of the Unified Development Code lists these districts:

          • Residential: R-A residential agriculture (1 acre minimum lot), R-1 single-family, R-2 two-family and R-3 multi-family.
          • Business: R-B, H-B, B-1, T-B, LB-2, B-2, B-3, B-4 and B-5.
          • Industrial and waterfront: CW, MM, ML, MH, I-1 and I-2, plus PD planned development.
          • Section 64-2-3 assigns annexed land to R-1 until a new district is adopted, unless the applicant asks for pre-zoning under Code of Alabama Section 11-52-85.

          What day are Mobile Planning Commission hearings?

          Hearings are held in person at 2 p.m. The 2026 dates posted on the Build Mobile Planning Commission page, from January 15 through November 19, all fall on the third Thursday of the month. The same page posts the filing deadlines.

            How do you look up zoning on a Mobile parcel?

            • Open the City of Mobile Planning and Zoning Public Viewer, or the PDF zoning map and future land use map on the Build Mobile maps page.
            • Our parcel viewer directory and zoning lookup guide cover county records.
            • Septic permits in Mobile County go through the Mobile County Health Department, Bureau of Environmental Health. The ADPH before-construction checklist explains the soil and sewer review.

            Mobile planning contacts

            • Build Mobile, Government Plaza, 205 Government Street, 3rd Floor, South Tower, Mobile, AL 36602. Phone 251-208-5895.

            Selling Mobile land that may need a rezoning

            Liberty Acres is an Atlanta-based, family-owned land buyer. We make offers on land as it is zoned today, or on terms that leave time for a rezoning while you keep title until closing. Closing can happen in as little as 14 days. See how rezoning-terms sales work or compare other Alabama rezoning guides.

            Want a written offer first? Liberty Acres buys land in this area. See sell land in Alabama.

              Common questions

              How much does a rezoning application cost in Mobile, AL?

              $500 per the March 2025 Planning Commission Application, plus postage for notices, a legal ad fee and recording costs.

              Is a neighborhood meeting required in Mobile?

              Yes, for a rezoning to a higher classification under Section 64-5-4. It is held on a weekday between 5 p.m. and 8 p.m., within 60 days before the Planning Commission hearing.

              Who makes the final rezoning decision in Mobile?

              The City Council, after a Planning Commission hearing and recommendation.

              How long before a denied Mobile request can come back?

              Not for six months after a Planning Commission recommendation to deny, a City Council denial or a withdrawal after notice.