Land entitlements in Sumner County, Tennessee

Sumner County bills new subdivisions per lot for plan review and inspection, on top of plat fees. Its rezoning process starts with a required meeting with staff. This guide covers who decides each approval in the county, Gallatin and Hendersonville, with the posted fees.

Sumner County land the current zoning holds back? See how we buy land that needs rezoning.

New: the Rezoning Approval Tracker lists every recent Nashville and Huntsville rezoning case with its outcome and days to a decision, plus a time and fee estimator and free CSV downloads.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

Who decides each entitlement in Sumner County?

In Sumner County, each approval has its own deciding body:

  • County rezoning: the Regional Planning Commission recommends, and the County Commission votes. A pre-application conference with staff is required under the zoning resolution.
  • A denied county rezoning generally bars the same request for one year.
  • County plats and site plans: the Regional Planning Commission, which meets at 5 pm on the third Tuesday at 355 North Belvedere Drive, Gallatin.
  • Special exceptions and variances: the county Board of Zoning Appeals. A special exception is typically renewed every two years.
  • Septic: Sumner is not one of the counties that run their own program, so permits come from TDEC.
  • Gallatin: the Planning Commission recommends, and the City Council decides. A denied request cannot be reconsidered for one year, under the zoning ordinance.
  • Hendersonville: the Planning Commission recommends, and the Board of Mayor and Aldermen decides.

What do entitlements cost in Sumner County?

We added up the county's fee schedule for a 10-lot residential subdivision. The preliminary plat is $300 and the final plat is $300. Plan review adds $200 per lot and construction inspection $100 per lot, or $3,000.

That is $3,600 in county fees before survey, engineering or construction. Subdivisions over 50 lots also need a traffic study, and its review costs $1,000.

A county rezoning is $1,000 plus a $25 sign fee. Gallatin charges $1,000 for a rezoning without a master plan, and Hendersonville charges $1,576.

Sumner County, Gallatin and Hendersonville entitlement fees

Official fees as published. Check the source before filing. Checked Nov 9, 2026.

WhereApplicationFeeSource
Sumner CountyRezoning$1,000 + $25 sign + $15 per added frontageSource
Sumner CountyConcept plat$250 (1 to 24 lots) or $500 (25 or more)Source
Sumner CountyPreliminary plat$300 for 6 to 10 lots + $50 per added lotSource
Sumner CountyFinal plat$300 for 6 to 10 lots + $50 per added lotSource
Sumner CountyMinor plat (5 lots or fewer)$250Source
Sumner CountySite plan$250Source
Sumner CountyResidential subdivision plan review$200 per lotSource
Sumner CountyConstruction inspection$100 per lotSource
Sumner CountyTraffic study review (over 50 lots)$1,000Source
Sumner CountySpecial exception$500Source
GallatinRezoning (no master plan)$1,000Source
GallatinPreliminary or final plat (1 to 25 lots)$500 + $25 per lotSource
GallatinMinor subdivision (1 to 2 lots)$300Source
HendersonvilleRezoning$1,576Source
HendersonvillePreliminary or final plat$1,628 eachSource
HendersonvilleConstruction plans$3,230Source
TDECNew conventional septic permit (to 1,000 gallons per day)$400 + $100 construction inspectionSource

How do you entitle land in Sumner County, step by step?

County land usually moves through these steps:

  • Confirm city or county and the zoning in the county property search.
  • Book the required pre-application conference with planning staff before a rezoning.
  • File the rezoning by the 3 pm deadline. Late applications move to the next month.
  • Start soil work with TDEC for any lot on septic.
  • File a concept plat, then the preliminary plat and construction plans.
  • Build or bond the improvements, pay the per-lot inspection fees, then file and record the final plat.

How long does entitlement take in Sumner County?

The Planning Commission meets monthly, with filing deadlines on the county's 2026 calendar. A rezoning then goes to the next County Commission meeting. Gallatin runs 13 review cycles a year. For recent rezoning timelines in Nashville and Huntsville, see the Rezoning Approval Tracker.

Where do you look up a Sumner County parcel?

Use the county property search for parcels and the Planning and Zoning page for the zoning map adopted July 29, 2024. Staff are at 355 North Belvedere Drive in Gallatin.

Who buys Sumner County land that still needs entitlements?

Liberty Acres is a family-owned land company based in Atlanta, Georgia. We buy land anywhere in the US, in any condition, including land that still needs approvals. On rezoning-terms deals, we handle the rezoning work and pay for it. For larger parcels with development potential, we can sign terms that allow time for zoning and entitlement work. You keep title until closing, closing comes later, and the price can reflect the value that work adds.

See selling Sumner County land that needs rezoning, the land entitlements guide, or the cost to rezone a property.

Land buyers like Liberty Acres can buy before a rezoning, on terms where we handle it and pay for it. More on sell land in Nashville, TN.

Common questions

How much does it cost to rezone land in Sumner County?

$1,000 plus a $25 sign fee, and $15 for each added road frontage. Gallatin charges $1,000 without a master plan, and Hendersonville charges $1,576.

How much does it cost to subdivide land in Sumner County?

For 10 lots, the county's posted fees come to $3,600. That covers the preliminary and final plats plus per-lot plan review and inspection.

Do I have to meet with Sumner County staff before a rezoning?

Yes. The county zoning resolution requires a pre-application conference before a rezoning request.

Who issues septic permits in Sumner County?

TDEC's Division of Water Resources. Sumner is not one of the counties that run their own septic program.

Can a denied Sumner County rezoning be refiled?

The same request is generally barred for one year after a denial. Gallatin has a one-year bar too.

Selling land near Gallatin or Hendersonville?

We can buy it as it is, or sign terms that leave room for zoning and entitlement work. How rezoning-terms sales work.

Closing can happen in as little as 14 days.

Get an offer on your land