Gallatin, the Sumner County seat, replaced its zoning ordinance on September 1, 2026 with a new code the City calls the ZOCO, built around character districts such as CD-2 and CD-4. Rezoning is now Section 21.1.19 of that code. A request starts with a required conference with Planning staff, runs through the Gallatin Municipal Planning Commission and ends with a first reading, a public hearing and a second reading at the City Council. This guide uses the new code, the 2026 meeting calendar and the fee schedule in effect since November 5, 2024.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

Gallatin's new code took effect in September 2026

The ZOCO adopted September 1, 2026 replaces the older article-based ordinance, and the new zoning map was adopted the same day. Districts now carry CD and SD labels: CD-1, CD-2A, CD-2, CD-3L, CD-3, CD-4, CD-4A, CD-4C, CD-5 and CD-CV, plus the special districts SD-HI, SD-RI and SD-LIV and the EPD district. Overlays such as the flood and airport overlays sit on top. If an older survey, plat or listing shows a district name from before September 2026, ask Planning what it is called now before you pick a target district.

Gallatin, TN planning fees

From the City of Gallatin fee schedule effective November 5, 2024. Checked Nov. 3, 2026. Checked Nov 9, 2026.

WhereApplicationFeeSource
GallatinRezoning$1,000Source
GallatinRezoning with a Preliminary Master Development Plan$1,000 plus $0.02 per square foot of nonresidential building and $10 per unitSource
GallatinComprehensive Plan amendment$1,000Source
GallatinAnnexation petition$500Source
GallatinAnnexation application$2,000 contiguous, $2,500 non-contiguousSource
GallatinSpecial-called Planning Commission meeting$1,000Source
GallatinSpecial-called City Council meeting$1,500Source
GallatinZoning or flood verification letter$50Source
GallatinSketch plat$100 plus $5 per lotSource
GallatinMinor subdivision (1 or 2 lots)$300Source
GallatinPreliminary or final plat (1 to 25 lots)$500 plus $25 per lotSource

Who can start a Gallatin rezoning

Section 21.1.19.D lets the City Council, the Planning Commission, the Zoning Administrator or the owner start a map change. An agent can file for the owner only with an agent letter. The application goes to the Zoning Administrator, who presents it to the Planning Commission before the Council sees it. The new boundary has to follow existing or future lot or parcel lines, and any part of the property left out must still be able to be subdivided and built under City rules.

What a Gallatin application needs by district

Section 21.1.19.F splits the paperwork by where you are headed.

  • To CD-4, CD-4A, CD-4C, CD-5 or SD-LIV: a Preliminary or Final Master Development Plan under Section 21.1.6.
  • To CD-1, CD-2A, CD-2, CD-3L, CD-3, SD-RI, SD-HI or CD-CV: a letter explaining how the change fits the Comprehensive Plan, a survey by a Tennessee-licensed surveyor with a legal description, slopes over 20 percent and floodplain acreage, and a list of adjoining owners from the latest Sumner County Assessor tax roll.
  • Every request: consistency with the Major Thoroughfare Plan, the Comprehensive Plan and other adopted City land use plans. A plan amendment can be filed at the same time, but it is decided by its own motion.

The pre-application conference Gallatin requires

The 2026 calendar says the City will not accept an application without a pre-application conference with staff. Call the Planning Department at 615-451-5796 to schedule it, well ahead of the Tuesday deadline you are aiming for. The Planning page describes a six-week review cycle from submittal to the Commission.

Gallatin submittal and resubmittal rules

  • File digitally through the self-service portal on the City website by 12:00 p.m. on the deadline.
  • The first upload includes the application form with the owner's signature or an agent letter, the checklist, supporting documents, the review fee, PDF and DWG files of the plan set and proof of ownership.
  • Staff inspect each package when it arrives. Incomplete packages are no longer accepted.
  • The resubmittal, due by noon on its own deadline, adds updated PDF and DWG files and a detailed letter answering every department's comments.

Gallatin Planning Commission dates for late 2026

The Commission usually holds a work session on the first Monday and its regular session on the fourth Monday, both at 5 p.m. in the Dr. J. Deotha Malone Council Chambers at City Hall. Dates marked as changes on the calendar move around holidays.

  • Submittal October 13, work session November 2, resubmittal November 5, meeting November 16, 2026.
  • Submittal November 10, work session November 30, resubmittal December 3, meeting December 14, 2026.
  • Submittal December 15, 2026, work session January 4, resubmittal January 11, meeting January 25, 2027.

Findings the Gallatin Commission and Council make

Under Section 21.1.19.H, the Commission records findings on plan consistency, the legal purposes of zoning, effects on adjoining owners, changed conditions or a mistake in the current zoning, and whether schools, roads, parks, wastewater, water and stormwater facilities are adequate. It has 60 days from the first hearing to recommend, with one more 30-day period allowed. After that, the Council can act without a recommendation.

The Council then holds an initial reading, a public hearing and a second reading, and may approve, approve with conditions, deny, send the request back or, with the applicant's consent, approve a less intensive district. A map change takes effect when the Council approves it unless the ordinance sets a later date.

Signs and newspaper notice in Gallatin

Section 21.1.4.D.1 has the City place a newspaper notice 21 to 30 days before the Council hearing, naming the current and proposed zoning. The Planning Department installs signs at least 10 days before the Planning Commission takes up the request, one for each 300 feet of street frontage where possible, within about 10 feet of the right-of-way. The signs stay up until the Council hearing. Newly annexed land getting its first zoning is exempt from the sign rule.

Denials, annexed land and the one-year wait

After a denial, Section 21.1.19.L bars a new rezoning of any part of the same property for one year. The exceptions are a request started by the Council or the Planning Commission, or a new request for a different district. Land annexed into Gallatin is zoned CD-2A automatically, so a rural tract coming into the City usually needs a rezoning after annexation if you want anything denser.

Gallatin plats and the subdivision rules

Lot creation follows the Subdivision Regulations, posted on the Subdivision Regulations page. The fee schedule charges $100 plus $5 a lot for a sketch plat, $300 for a minor subdivision of one or two lots, and $500 plus $25 a lot for a preliminary or final plat of up to 25 lots. A rezoning boundary that cuts a parcel must leave the remainder subdividable under these rules.

Gallatin zoning map, GIS and septic

Gallatin Planning Department contacts

Selling Gallatin land before it is rezoned

Gallatin land can sell under the zoning it holds today, even after the September 1, 2026 ZOCO rewrite. Liberty Acres underwrites Sumner County parcels against the new character districts, access and comps, then makes a written offer. Sellers pay no fees or commissions; we pay closing costs.

When a CD district change is what a buyer would want later, we can buy as-is or on rezoning terms where we handle the pre-application conference and the Section 21.1.19 filings. Closing can happen in as little as 14 days. Compare Sumner County land and land that needs rezoning.

We buy land here as it is zoned or with the rezoning still ahead. For the local details, see sell land in Nashville, TN.

Common questions

Do I need a meeting before I file a Gallatin rezoning?

Yes. The 2026 calendar says applications are not accepted without a pre-application conference. Call 615-451-5796.

What district does annexed land get in Gallatin?

CD-2A, automatically, under Section 21.1.19.M of the ZOCO.

How far ahead is a Gallatin rezoning hearing advertised?

21 to 30 days before the City Council public hearing, in a local newspaper.

When does the Gallatin Planning Commission meet in December 2026?

December 14, 2026 at 5 p.m., after a November 30 work session. The submittal deadline was November 10.

Which Gallatin rezonings need a master development plan?

Requests to CD-4, CD-4A, CD-4C, CD-5 or SD-LIV, under Section 21.1.19.F.4.

Does Gallatin’s new ZOCO stop me from selling now?

No. The September 2026 code change affects how a rezoning is filed, not whether you can sell under current zoning. Liberty Acres buys Gallatin land as-is; closing can happen in as little as 14 days.

Rather skip the conference and the two readings?

We buy Gallatin land as it is zoned, or on terms where we prepare and file the request and attend the hearings while you keep title until closing. How rezoning-terms sales work.

Closing can happen in as little as 14 days.

Send us your parcel

Sources