How long does it take to rezone a property in Tennessee?

Metro Nashville says a zone change takes 3 to 6 months if there are no complications. Most counties and cities around Nashville do not publish one number. Their 2026 calendars, notice rules and readings show where the time goes. Here is each step, with official examples from Middle Tennessee.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

The steps that set the clock

Rezonings around Nashville follow the same basic path. A planning commission reviews the request. Then the elected body holds a public hearing and votes.

For fees, see how much it costs to rezone land in Tennessee.

The statewide process, who votes, and the local guide directory are in how to rezone land in Tennessee.

  • Meetings before you file. Williamson County requires a pre-application conference at least 10 days before the agenda deadline. Maury County requires a staff conference and a neighborhood meeting.
  • The filing deadline. Most planning commissions close each agenda weeks before the meeting, so missing one date can cost a month.
  • Planning commission review. Cheatham and Dickson county rules give the planning commission 30 days to report.
  • Public notice. Robertson County and many cities publish notice at least 15 days before the hearing. Cheatham and Dickson counties require at least 30 days.
  • Readings. Metro Nashville's Council takes three readings, and so does Franklin's Board of Mayor and Aldermen. Springfield and Smyrna use two.

From filing deadline to planning commission

These examples come from each local government's own 2026 calendar.

  • Robertson County: an October 16 deadline leads to the November 19 meeting.
  • Springfield: an October 28 initial submittal leads to the December 3 meeting.
  • Cheatham County: an October 8 deadline leads to the November 5 meeting.
  • Ashland City: an October 27 submittal shutoff leads to the December 7 meeting.
  • Columbia: an October 19 filing leads to the December 9 meeting, after a pre-application meeting by October 7.
  • Spring Hill: a September 21 deadline leads to a November 9 vote.
  • Gallatin: an October 13 deadline leads to a November 16 meeting.

That is only the first vote. The elected body still has to hold its hearing and readings.

From filing deadline to planning commission, 2026 calendars

From each local government's published 2026 schedule. The elected board's hearing and votes follow the planning commission. Checked Nov 10, 2026.

JurisdictionFiling deadlinePlanning commission meetingSource
Robertson CountyOct 16Nov 19Source
SpringfieldOct 28Dec 3Source
Cheatham CountyOct 8Nov 5Source
Ashland CityOct 27Dec 7Source
ColumbiaOct 19Dec 9Source
Spring HillSep 21Nov 9Source
GallatinOct 13Nov 16Source

From planning commission to final vote

Rutherford County's 2026 schedule puts about 11 weeks between one filing deadline and the final vote.

In Metro Nashville, the Council considers a rezoning on three readings: introduction, a public hearing and a final vote. In Franklin, a rezoning takes effect when it passes third reading.

Springfield's Board of Mayor and Aldermen holds a public hearing, then takes the ordinance on second and final reading.

What adds time

  • Studies. Robertson County keeps a request off the agenda until a required traffic study is in. Spring Hill asks for a water and sewer capacity study.
  • Water letters. Columbia requires a water availability letter for every rezoning, and it can take time.
  • Deferrals. In Rutherford County, a deferral can last up to three months.
  • A no vote. Refiling waits six months in Robertson and Rutherford counties and one year in Williamson County.
  • Holidays. Calendars shift meetings near the end of the year, as Robertson County's 2026 calendar does for November and December.

For the local steps, see the guides for Robertson County, Cheatham County, Dickson County and Nashville.

Selling while a rezoning is pending

You do not have to wait out the rezoning to sell. Liberty Acres buys land anywhere in the US, in any condition. Selling to us is easy.

Land buyers like Liberty Acres can buy before a rezoning, on terms where we handle it and pay for it. More on sell land in Tennessee.

  • We can make an offer on the land as it is zoned today.
  • For larger parcels with development potential, we can sign terms that allow time for the rezoning. We handle that work.
  • You keep title until closing, and the price can reflect the added value.
  • We're flexible on terms. We'll do what makes sense for your situation.
  • We can pay back taxes, and we pay all closing costs. No agents and no commissions.

Closing can happen in as little as 14 days. On rezoning terms, closing waits for the approvals.

This is general information, not legal or tax advice. Talk to a local real estate attorney about your situation.

Common questions

How long does rezoning take in Nashville?

Metro Nashville says a zone change takes 3 to 6 months if there are no complications. The Metro Council decides on three readings.

How long from filing to the planning commission in Middle Tennessee?

On 2026 calendars it is often four to seven weeks. Robertson County runs October 16 to November 19, and Springfield runs October 28 to December 3.

How much notice comes before a rezoning hearing in Tennessee?

Robertson County and many cities publish notice at least 15 days ahead. Cheatham and Dickson counties require at least 30 days.

How soon can I refile after a rezoning is denied?

It depends on the place. Robertson and Rutherford counties use six months, and Williamson County uses one year.

Can I sell my land while a rezoning is pending?

Yes. We can make an offer on the land as it is zoned today, or sign terms that allow time for the rezoning on larger parcels.

Rather hand off the rezoning?

On rezoning-terms deals, we do the work and pay for it, and you keep title until closing. Read how it works.

Closing can happen in as little as 14 days.

Request my offer

Sources