How to rezone land in Hendersonville, Tennessee

Hendersonville is the largest city in Sumner County and zones its land under a Zoning Ordinance most recently amended by Ordinance 2026-10 on September 22, 2026. A map amendment goes to the Hendersonville Regional Planning Commission for a public hearing and findings, then through the General Committee to the Board of Mayor and Aldermen for two readings. The City posts a submittal schedule through early 2027 and a fee schedule effective January 1, 2026, and both are summarized below with the code sections behind them.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

Hendersonville's ordinance and the 2026 amendments

The Zoning Ordinance posted by the Planning Department lists Ordinance 2026-10, adopted September 22, 2026, on its cover, along with Ordinance 2025-19, effective November 18, 2025. The file name still says 2019-45, the revision it started from, so check the cover date when you download it. Chapter 4.8 covers text and map amendments, Chapter 3.3 covers notice, and Appendix A charts the annexation, rezoning, development plan, subdivision and site plan processes.

Hendersonville, TN planning fees

From the City of Hendersonville 2026 fee schedule, effective January 1, 2026. Checked Nov. 3, 2026. Checked Nov 10, 2026.

WhereApplicationFeeSource
HendersonvilleRezoning$1,576Source
HendersonvilleAnnexation$1,681Source
HendersonvilleZoning text amendment$1,891Source
HendersonvilleFuture Land Use Plan amendment$1,156Source
HendersonvillePreliminary Development Plan$3,992Source
HendersonvilleFinal Development Plan$2,627Source
HendersonvilleCombined Development Plan$4,518Source
HendersonvilleSketch plat$247Source
HendersonvilleMinor subdivision$998Source
HendersonvillePreliminary or final plat$1,628Source
HendersonvilleZoning verification letter$27Source
HendersonvilleEach additional corrected plan set$210Source

Section 4.8: from application to Board vote

For the statewide steps and other Tennessee city and county guides, see how to rezone land in Tennessee.

  • The City, an owner of property in the City or the owner's authorized agent may file (Section 4.8.2).
  • Planning schedules a complete application for the Planning Commission, which must hold its public hearing within 60 days. A request for more information pauses that clock.
  • Within 45 days after the hearing closes, the Commission sends its recommendation and findings to the Board of Mayor and Aldermen through the General Committee.
  • The Board acts within 30 days of receiving the report, approves or denies on two separate readings by simple majority, and holds a public hearing before final approval. It may also refer the request back to the Commission.

The three Hendersonville rezoning findings

Section 4.8.4 asks the Commission and the Board to find that the change agrees with the Land Use Plan, that it has no significant adverse effect on adjoining owners unless the public good outweighs it, and that conditions in the area have changed enough to justify amending the Land Use Plan, if needed, and then the map. A request tied to a Planned Development follows Section 8.8.3.2.B instead. Land that was never given a district is treated as SR-1 under Section 5.3.1.

Mailed, posted and published notice in Hendersonville

Chapter 3.3 requires mailed and posted notice for the Planning Commission hearing and mailed and published notice for the Board hearing.

  • Published notice: 15 to 30 days before the hearing, and at least 21 days before the Board hearing to meet Tenn. Code Ann. 13-7-203(a).
  • Mailed notice: the Planning Department mails owners within 250 feet, taken from the Sumner County Assessor GIS records, 15 to 30 days ahead and keeps an affidavit of mailing.
  • Posted notice: the City places a sign on each street frontage 15 to 30 days before the hearing.

Hendersonville's Rezoning application form

The Rezoning application, revised January 28, 2022, is for a regular rezoning. A Planned Development rezoning uses a separate form, and both are listed on the Application Submittal Information page. The form asks for the map group and parcel, the Future Land Use and Transportation Plan designation, the water, sewer, gas and electric providers, the road the land fronts and the feet of new road proposed. Attach a copy of the deed, a letter explaining the request and a map, with PDF and DWG files.

The City treats its deadlines as final. A project deferred or inactive for three months or more may expire.

How Hendersonville takes digital submittals

  • Initial submittal by 12:00 PM on the deadline, emailed to planning@hvilletn.org as PDF plus a projected shapefile in NAD 1983 State Plane Tennessee.
  • Staff confirm acceptance within two business days, and fees are due by the end of the submittal week.
  • The resubmittal is due by 9:00 AM with every change clouded on the plans.
  • Final responses to comments are due by 9:00 AM on the Friday before the meeting.

Hendersonville Planning Commission dates into 2027

The submittal schedule, revised October 26, 2026, pairs each 6:30 PM Planning Commission meeting with four earlier dates: initial submittal, comments, resubmittal and the final response.

  • Initial submittal November 9, comments December 2, resubmittal December 10, final response December 16, meeting January 5, 2027.
  • Initial submittal November 16, comments December 16, resubmittal January 4, final response January 20, meeting February 2, 2027.
  • Initial submittal December 14, comments January 13, resubmittal January 28, final response February 11, meeting March 2, 2027.

Meetings are normally on the first Tuesday at City Hall, 101 Maple Drive North, per the Planning Commission page.

Hendersonville fees for a map change and what follows

The 2026 fee schedule took effect January 1, 2026. A straight rezoning is $1,576. Planned Development work is priced separately: $3,992 for a Preliminary Development Plan, $2,627 for a Final Development Plan and $4,518 for a Combined Development Plan, so ask staff which items apply before you file. A Future Land Use Plan amendment adds $1,156 when the map change needs one. Each extra corrected plan set is $210.

Platting land after a Hendersonville rezoning

The Subdivision Regulations were readopted by Resolution 2026-02 on July 7, 2026. The fee schedule lists $247 for a sketch plat, $998 for a minor subdivision and $1,628 for a preliminary or final plat. If the land sits near the edge of town, the urban growth boundary map shows whether the City can annex it, and annexation is $1,681.

Hendersonville maps and parcel records

Sewer and septic around Hendersonville

The application asks who supplies water and sewer, so confirm service before you file. Where there is no sewer, septic permits in Sumner County go through the TDEC Nashville Environmental Field Office, 711 R.S. Gass Blvd., Nashville, TN 37216, (615) 687-7000. Our water, sewer and septic guide explains how capacity can shape what a district allows.

Hendersonville Planning Department

  • Planning Department, 101 Maple Drive North, Hendersonville, TN 37075. Phone 615-264-5316, planning@hvilletn.org, Monday to Friday 8:00 to 4:30. Planning page.
  • City Hall main line: 615-822-1000.
  • Unincorporated land: see the Sumner County data page.

Selling Hendersonville land before it is rezoned

Hendersonville owners can sell without waiting on Ordinance 2026-10 map amendments. Liberty Acres prices Sumner County shoreline and inland parcels from current zoning, septic or sewer status and recent sales, then issues a written offer. No fees or commissions, and we pay closing costs.

If a Board of Mayor and Aldermen map change is part of the upside, rezoning terms let us carry the $1,576 application, shapefile submittal and hearings while you keep title until closing. Closing can happen in as little as 14 days. See how selling works and Sumner County context.

Want a written offer first? Liberty Acres buys land in this area. See sell land in Nashville, TN.

Common questions

What file format does Hendersonville want with a rezoning?

PDF plus a projected shapefile in NAD 1983 State Plane Tennessee, emailed to planning@hvilletn.org. The application also asks for DWG files.

How far does Hendersonville mail rezoning notices?

To owners within 250 feet, 15 to 30 days before the hearing, under Chapter 3.3 of the Zoning Ordinance.

How long does the Hendersonville Planning Commission have to hear a rezoning?

It must hold the public hearing within 60 days of a complete application and report within 45 days after that.

Which zoning applies to unzoned land in Hendersonville?

SR-1, under Section 5.3.1 of the Zoning Ordinance.

When is the next Hendersonville Planning Commission meeting I can still make?

On the schedule revised October 26, 2026, a November 9 initial submittal goes to the January 5, 2027 meeting.

Do I need Board approval before selling Hendersonville land?

Not to sell as zoned. Board of Mayor and Aldermen readings matter for map amendments. Liberty Acres can buy the parcel first and handle a later rezoning on terms if that fits the deal.

Rather not build the shapefile and submittal package?

We buy Hendersonville land as it is zoned, or on terms where we prepare and file the request and attend the hearings while you keep title until closing. How rezoning-terms sales work.

Closing can happen in as little as 14 days.

Send us your parcel

Sources