Portland sits on the line between Sumner and Robertson counties, and the city zones land on both sides under its Zoning Ordinance, last amended in February 2026. Sections 14-602 through 14-608 govern amendments: the Planning Commission reviews and recommends, and City Council adopts a rezoning by ordinance on two readings, with the public hearing at the second. Every submittal starts with a required pre-application meeting and goes in through the city's IDT Plans portal.

Portland land that its current zoning holds back? See how we buy land that needs rezoning.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

One city, two counties

Portland's rezoning application asks you to circle Sumner County or Robertson County, because the city limits cross both. The city process is the same either way. Land outside the city limits goes to that county's own planning commission instead.

Portland, TN rezoning and plat fees

From the City of Portland Planning and Zoning Fee Schedule page. The application fee is non-refundable. Checked Nov. 3, 2026. Checked Nov 9, 2026.

WhereApplicationFeeSource
PortlandRezoning, up to 0.99 acres$300Source
PortlandRezoning, 1 to 9 acres$350Source
PortlandRezoning, 10 to 19 acres$400Source
PortlandRezoning, 20 to 49 acres$500Source
PortlandRezoning, 50 to 99 acres$600Source
PortlandRezoning, 100 acres or more$700Source
PortlandAnnexation$500Source
PortlandAnnexation, non-contiguous$1,000Source
PortlandPUD preliminary master development plan$1,000 plus $0.02 per sq. ft. of non-residential building and $10 per dwelling unitSource
PortlandConcept subdivision$150 plus $5 per lotSource
PortlandPreliminary plat$300 plus $25 per lotSource
PortlandFinal plat$500 plus $25 per lotSource
PortlandZoning ordinance amendment$200Source

The pre-application meeting comes first

It is mandatory. The Planning Commission page says a pre-application meeting with city staff is required before any submittal, and at that meeting you name one contact person to work with staff for the whole project. Meetings for site plans and plats that need Commission approval must be at least three weeks before submittal. Other projects may meet one week before. The City Planner schedules them.

Filing through IDT Plans

  • The rezoning application, an agent authorization form, a legal description, a copy of the recorded deed, and an 8.5 by 11 inch map with the property highlighted.
  • If you are not the owner: a notarized letter of consent, a purchase contract with a zoning contingency, or the agent authorization form.
  • Tax map and parcel numbers, total acreage, and current and requested zoning.
  • Upload everything to the city's IDT Plans portal, where Planning, Engineering, Public Works, Codes and Utilities staff review submittals.

Article XIV hearing and notice rules

Under Section 14-605 of the Zoning Ordinance, the Commission and Council must make findings: the change fits the general plan, does not contravene the purposes of zoning, does not harm adjoining owners without an overwhelming public benefit, does not reward one owner at the public's expense, and responds to changed conditions.

Section 14-606 requires newspaper notice 15 to 30 days before the Council hearing, with a graphic of the area, and a sign on the property at least 15 days before. Under Section 14-608, a denied request cannot come back for one year unless it asks for a different district, Council or the Commission starts it, or the general plan has since changed.

Portland rezoning fees by acreage

The city's Planning and Zoning Fee Schedule prices a rezoning by size, from $300 under one acre to $700 at 100 acres or more. Annexation is $500, or $1,000 if the land is not contiguous. The application fee is non-refundable.

2026 and January 2027 Commission dates

The 2026-2027 calendar sets noon submittal deadlines about four weeks before each 5:00 pm meeting in Council Chambers, Room 111, at City Hall.

  • December 8, 2026 meeting: submit by November 11. Resubmit by December 2.
  • January 12, 2027 meeting: submit by December 9, 2026. Resubmit by January 6, 2027.
  • The Commission can change the calendar with at least two months of notice.

PUD rules and Table 6-301A lot sizes

Section 12-301 requires a new PUD to cover at least 2 acres, and any rezoning request with a multi-family part, meaning buildings of three or more units, must be filed under the PUD article regardless of acreage. Table 6-301A sets the residential minimums:

  • RS-40 and R-40: 40,000 square feet, 100 feet wide.
  • RS-20: 20,000 square feet, 100 feet wide.
  • RS-15 and R-15: 15,000 square feet, 75 feet wide.
  • R-10: 10,000 square feet, 60 feet wide.
  • R-7.5: 7,500 square feet, 60 feet wide.
  • RM-1: 6,000 square feet, 50 feet wide.

Portland subdivision review

The Subdivision Regulations, updated February 10, 2026, have the City Planner classify each plat as major or minor. A plat that needs a new or extended street or required improvements gets major review. Concept plans are $150 plus $5 per lot, preliminary plats $300 plus $25 per lot and final plats $500 plus $25 per lot.

Portland GIS and parcel tools

Septic permits on both sides of the county line

The TDEC Nashville Environmental Field Office, 711 R.S. Gass Boulevard, Nashville, (615) 687-7000, covers both Sumner and Robertson counties. On lots without city sewer, soil decides how small you can go, so read our perc test guide before asking for R-10 or smaller.

Portland Planning and Zoning contacts

  • Planning and Zoning, City Hall, 100 S. Russell Street, Portland, TN 37148. Phone 615-325-6776, ext. 239. Hours 8:00 am to 4:30 pm weekdays.
  • Help with IDT Plans submittals: the Planning Department, 615-325-6776, ext. 227.
  • Septic: TDEC Nashville office, (615) 687-7000.

Selling Portland land in Sumner or Robertson County

We buy Portland land in either county as it is zoned, or on rezoning terms where we hold the pre-application meeting, file through IDT Plans and attend both Council readings while you keep title until closing. Closing can happen in as little as 14 days. See how rezoning-terms sales work, the Sumner County rezoning page and the Robertson County rezoning page.

Want a written offer first? Liberty Acres buys land in this area. See sell land in Nashville, TN.

Common questions

How much is a rezoning in Portland, TN?

$300 under one acre, rising by acreage to $700 for 100 acres or more, per the city fee schedule.

Is a pre-application meeting required in Portland?

Yes. The city requires one with staff before any submittal. The City Planner schedules it.

When is the next Portland Planning Commission meeting?

Tuesday, December 8, 2026 at 5:00 pm, with a November 11 submittal deadline. The January 12, 2027 meeting has a December 9 deadline.

Can a denied Portland rezoning be refiled?

Not for one year, unless it asks for a different district, Council or the Commission initiates it, or the general plan changed, under Section 14-608.

Does Portland zoning cover land in Robertson County?

Yes, for land inside Portland city limits. The rezoning application asks which county the parcel is in.

Rather skip the pre-application meeting and IDT Plans?

We buy Portland land in Sumner or Robertson County as it is zoned, or on terms where we file and attend the hearings. How rezoning-terms sales work.

Closing can happen in as little as 14 days.

Send us your parcel