How to rezone land in Thompson's Station, Tennessee

Thompson's Station is a Williamson County town between Franklin and Spring Hill whose Land Development Ordinance was last updated December 18, 2025. A rezoning there has more front-end steps than most Middle Tennessee towns: a preapplication meeting, at least one neighborhood meeting, and a joint workshop with the Planning Commission and the Board of Mayor and Aldermen before the formal file is reviewed. This guide follows the LDO, the 2026 submittal schedule and the fee schedule approved by Ordinance 2026-013.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

Six steps in LDO Section 2.4.3

  • A preapplication meeting with staff.
  • At least one neighborhood meeting before the Planning Commission submittal, with a written summary of what neighbors said.
  • A joint informal workshop with the Planning Commission (TSPC) and the Board of Mayor and Aldermen (BOMA).
  • The formal application and staff review.
  • A TSPC recommendation.
  • A BOMA decision. If the TSPC recommends against the change, approval takes a two-thirds BOMA majority.

The Land Development Ordinance, posted on the Town's LDO page, is the controlling text.

Thompson's Station, TN planning fees

From the Town fee schedule page; the Town says the fees approved by Ordinance 2026-013 began July 1, 2026. Checked Nov. 3, 2026. Checked Nov 9, 2026.

WhereApplicationFeeSource
Thompson's StationRezoning$600Source
Thompson's StationAnnexation$300 (5 acres or less), $600 (more than 5 acres)Source
Thompson's StationPreliminary development plan$1,050Source
Thompson's StationSite plan$400 plus $0.02 per square footSource
Thompson's StationConstruction documents$650Source
Thompson's StationPreliminary plat$300 plus $50 per acreSource
Thompson's StationMinor final plat$250Source
Thompson's StationMajor final plat$400 plus $25 per lotSource
Thompson's StationBoard of Zoning Appeals$100Source

How the Town judges a rezoning request

Staff and both boards weigh consistency with the Town's policy plan and the load the change puts on transportation, sewer, water from the HB&TS Utility District, the Williamson County School District, parks and emergency services. Because the joint workshop comes before the formal filing, those concerns usually surface early, while the plan can still change.

Thompson's Station deadlines from Plan Meeting to filing

The Land Development Manual, revised May 15, 2025, starts with a Plan Meeting. The preapplication meeting has to follow within 90 days, and the formal application within 120 days after that. Applications and plans are filed through the Town's GeoCivix portal.

What the rezoning checklist asks for

  • A surveyed boundary of the land.
  • The zoning of all property within 500 feet.
  • A sewer statement showing how the land will be served.
  • Where a wastewater reservation is involved, a 25 percent reservation deposit due within 90 days of the rezoning.

Letters, signs and newspaper notice in Section 2.3

The applicant mails notice by first class mail to every owner within 1,056 feet and signs an affidavit that it went out. Table 2-2 sets the letter and the property sign at 21 days before the TSPC meeting and the newspaper notice at 21 days before the BOMA public hearing on second reading. Notice of the neighborhood meeting goes out 10 days ahead.

2026 TSPC submittal schedule

The 2026 schedule runs each case through a joint workshop, initial submittal, staff review and final submittal before the meeting. There is no December TSPC meeting in 2026.

  • November cycle meeting December 1, 2026: joint workshop August 31, initial submittal October 13, final submittal November 6.
  • January 2027 meeting on January 26: joint workshop November 2, 2026, initial submittal December 8, final submittal January 1.

When the TSPC and BOMA meet

The Planning Commission page lists regular meetings on the fourth Tuesday at 6:00 p.m. at Town Hall. The Commission has five members plus one alderman and one mayoral appointee, on three-year terms. The manual has the BOMA, which typically meets on the second Tuesday, take the rezoning ordinance through three readings, with the public hearing at the second.

Thompson's Station plats and site plans

The fee schedule charges $300 plus $50 an acre for a preliminary plat, $250 for a minor final plat and $400 plus $25 a lot for a major final plat. A preliminary development plan is $1,050 and a site plan $400 plus 2 cents a square foot. All fees are paid before plan or permit review.

Thompson's Station zoning map and GIS

Septic in Thompson's Station

Where a lot will not connect to Town wastewater, approval comes from Williamson County Sewage Disposal Management, (615) 790-5751, which reviews soils and issues septic permits in the county.

Thompson's Station Town Hall

Selling Thompson's Station land before it is rezoned

Liberty Acres, based in Atlanta, buys Thompson's Station land as it is zoned, or on rezoning terms where we prepare and file the request, run the neighborhood meeting and attend the hearings while you keep title until closing. Closing can happen in as little as 14 days. Read how rezoning-terms sales work or rezoning land in Williamson County.

Land buyers like Liberty Acres can buy before a rezoning, on terms where we handle it and pay for it. More on sell land in Nashville, TN.

Common questions

Is a neighborhood meeting required for a Thompson's Station rezoning?

Yes. Section 2.4.3 requires at least one before the Planning Commission submittal, with a written summary, and notice goes out 10 days ahead.

How far out does Thompson's Station mail rezoning notices?

1,056 feet, by first class mail from the applicant, 21 days before the Planning Commission meeting.

Is there a December 2026 Thompson's Station Planning Commission meeting?

No. The 2026 schedule has the November cycle meeting on December 1 and the next on January 26, 2027.

What does it cost to rezone in Thompson's Station?

$600, paid before review, under the fee schedule approved by Ordinance 2026-013.

How many BOMA readings does a Thompson's Station rezoning take?

Three, with the public hearing at the second reading.

Rather skip the neighborhood meeting and workshop?

We buy Thompson's Station land as it is zoned, or on terms where we prepare and file the request and attend the hearings while you keep title until closing. How rezoning-terms sales work.

Closing can happen in as little as 14 days.

Send us your parcel

Sources