← Guides

Land entitlements in Rutherford County, Tennessee

In unincorporated Rutherford County, per-lot fees matter more than the application fee. The county charges per lot for plats, plan review, land disturbance and inspection. This guide shows who decides each approval in the county, Murfreesboro and Smyrna, with the posted fees.

Rather not pay Rutherford County's plat and review fees yourself? Read how we buy land before it's entitled.

New: the Rezoning Approval Tracker lists every recent Nashville and Huntsville rezoning case with its outcome and days to a decision, plus a time and fee estimator and free CSV downloads.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

Who decides each entitlement in Rutherford County?

The approvals split like this:

  • County rezoning: the Regional Planning Commission recommends and the Board of Commissioners votes. The county's 2026 calendar shows no Board meeting in July.
  • A denied county rezoning generally cannot come back for six months, under Section 1409 F of the county zoning ordinance.
  • County plats and site plans: the Regional Planning Commission. Planning and Engineering review construction plans, land disturbance and inspections.
  • County variances and special exceptions: the Board of Zoning Appeals.
  • Septic: Rutherford is not one of the counties that run their own program, so permits come from the TDEC Division of Water Resources field office.
  • Murfreesboro: the Planning Commission recommends, then the City Council holds its own hearing and votes on two readings.
  • Smyrna: the Planning Commission recommends, and the Town Council votes on two readings.

What do entitlements cost in Rutherford County?

We added up the county's posted fees for a 10-lot major subdivision. The preliminary plan is $8,500 and the final plat is $8,500. Construction plan review, land disturbance and inspection add $1,600 per lot, or $16,000.

That is $33,000 in county fees, or $3,300 per lot, before any survey, engineering or construction. The same 10 lots inside Murfreesboro pay $2,000 in plat fees.

A straight county rezoning is $1,000. The county does not refund planning fees.

Rutherford County, Murfreesboro and Smyrna entitlement fees

Official fees as published. Check the source before filing. Checked Nov 9, 2026.

WhereApplicationFeeSource
Rutherford CountyRezoning (not PUD)$1,000Source
Rutherford CountyPUD rezoning$1,000 + $10 per unit and/or $0.02 per sq ftSource
Rutherford CountyPreliminary plan$1,000 + $750 per lotSource
Rutherford CountyMajor final plat$1,000 + $750 per lotSource
Rutherford CountyMinor final plat$250 + $100 per lotSource
Rutherford CountyConstruction plan review$600 per lotSource
Rutherford CountyLand disturbance (subdivision)$600 per lotSource
Rutherford CountyConstruction inspection$400 per lotSource
Rutherford CountyVariance or special exception$750Source
MurfreesboroRezoning$700, or $950 for a PUDSource
MurfreesboroPreliminary plat$400 + $85 per lotSource
MurfreesboroFinal plat$200 + $55 per lotSource
MurfreesboroAnnexation$2,000Source
SmyrnaRezoning$750, or $1,000 for a planned developmentSource
SmyrnaPreliminary plat$600Source
SmyrnaFinal plat$500Source
TDECNew conventional septic permit (to 1,000 gallons per day)$400 + $100 construction inspectionSource

How do you entitle land in Rutherford County, step by step?

A typical order for county land:

  • Confirm city or county and the zoning on the county GIS Data Hub.
  • For lots on septic, start the soil review with TDEC early. Lot count often depends on it.
  • If the zone has to change, file the rezoning first and wait for the Board of Commissioners vote.
  • File the preliminary plan with construction plans, and budget for the per-lot engineering fees.
  • Get a land disturbance permit before grading, then build or bond the improvements.
  • File the final plat and record it once it is signed.
  • If a rule blocks the plan, ask the Board of Zoning Appeals for a variance or special exception.

How long does entitlement take in Rutherford County?

On the county's 2026 calendar, a rezoning runs about 11 weeks from the filing deadline to the Board of Commissioners vote. TDEC says septic permit reviews generally take 10 days and must finish within 45 days of a complete application.

Murfreesboro runs 13 plan review cycles a year. For recent rezoning timelines in Nashville and Huntsville, see the Rezoning Approval Tracker.

Where do you look up a Rutherford County parcel?

The county GIS Data Hub has zoning and parcel layers. The GIS office is at 20 North Public Square, Suite 410, Murfreesboro, (615) 898-7762. Planning is at 1 South Public Square, Room 200, at (615) 898-7730, and Engineering is at (615) 898-7732.

Who buys Rutherford County land that still needs entitlements?

Liberty Acres is a family-owned land company based in Atlanta, Georgia. We buy land anywhere in the US, in any condition, including land that still needs approvals. On rezoning-terms deals, we handle the rezoning work and pay for it. For larger parcels with development potential, we can sign terms that allow time for zoning and entitlement work. You keep title until closing, closing comes later, and the price can reflect the value that work adds.

See selling Rutherford County land that needs rezoning, the land entitlements guide, or the cost to subdivide land.

To skip the hearings, you can sell your land to us and let us handle the rezoning. See sell land in Nashville, TN.

Common questions

How much does it cost to subdivide land in Rutherford County?

For 10 lots in the unincorporated county, the posted fees come to $33,000. That is $17,000 for the preliminary plan and final plat, plus $16,000 in per-lot engineering and inspection fees.

How much is a rezoning in Rutherford County?

$1,000 in the unincorporated county. Murfreesboro charges $700, and Smyrna charges $750.

Who issues septic permits in Rutherford County?

TDEC's Division of Water Resources, through its field office. A new conventional permit is $400 for up to 1,000 gallons per day, plus a $100 construction inspection.

How much is a variance in Rutherford County?

$750 at the county Board of Zoning Appeals. Murfreesboro's BZA fee is $350, and Smyrna's is $300.

Can a denied Rutherford County rezoning be refiled?

Generally not for six months, under Section 1409 F of the county zoning ordinance.

Have acreage near Murfreesboro or Smyrna?

On rezoning-terms deals, we handle the rezoning work and pay for it. Learn how selling land that needs rezoning works.

Closing can happen in as little as 14 days.

Request my offer

Sources