How to rezone land in Nashville and Davidson County
To rezone land in Nashville, you file a zone change with Metro Planning, the Planning Commission makes a recommendation, and the Metro Council decides after three readings. This guide walks through each step with Metro's current fees, deadlines, notice rules and contacts, all taken from Metro's own documents.
Want to rezone Davidson County land without running Metro's process yourself? See how we buy land that needs rezoning.
New: the Rezoning Approval Tracker lists every recent Nashville and Huntsville rezoning case with its outcome and days to a decision, plus a time and fee estimator and free CSV downloads.
New research: the Nashville & Huntsville Rezoning Report 2026 shows which rezoning requests pass, which stall after a deferral and how long a decision takes, from 373 recent cases, with free charts and data.
New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.
Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.
New: the free Davidson County lot split checker looks up any Nashville parcel by address or parcel ID and shows its zoning, minimum lot size, the most lots by area alone, and floodplain and steep slope flags.
Who decides a rezoning in Nashville?
Nashville and Davidson County share one Metro government, so one process covers the county. Metro Planning staff review the application and write a staff report. The Metropolitan Planning Commission holds a public hearing and makes a recommendation. The Metro Council makes the final decision on every zone change, and the Mayor signs or vetoes the bill.
Your district councilmember plays the biggest single role. Metro's application says you must contact the district councilmember before you submit it, and you attach a copy of that email to the councilmember and the Metro Council Office. The councilmember sponsors the rezoning ordinance, and Metro says councilmembers often host meetings with the neighbors who would be affected. Under the Council's rules, a bill that affects only one district is deferred one meeting on request when that district's member is not a sponsor. Find your member on the Metro Council districts page.
The Commission's vote is a recommendation, and the Council agenda shows it on every zoning bill. Council rules require a roll call vote on third reading for any zoning matter the Commission disapproved.
Nashville is one of many local processes in the state. For the statewide steps and a directory of Tennessee city and county guides, see how to rezone land in Tennessee.
What are the steps to rezone land in Davidson County?
Metro lists seven steps from application to the Mayor's signature. Here is the full sequence, with the preparation that comes before it.
- Check the zoning and the policy. Look up the parcel's current zoning and its Community Character policy in the Parcel Viewer. Metro's application says Planning is highly unlikely to recommend approval of a district the policy does not support.
- Send a pre-application inquiry. Email the form to planningstaff@nashville.gov. Metro says it is recommended but not mandatory, and a planner typically responds by email within a week. A straight rezoning does not need a sketch plan.
- Talk to the councilmember and the neighbors. Then email the district councilmember and the Metro Council Office about the request, and keep a copy for the application.
- Get a Planning Portal account. Metro does not accept paper applications, and it says a username and password can take several days.
- File by a deadline. Upload the application, a map, entity signatory documents if an entity owns the land, and proof that property taxes are current at least 48 hours before the deadline (Metro's 2027 schedule). The fee is due by noon on the deadline. The Commission's rules require zone changes to be filed at least 42 days before the meeting.
- Staff review. Planning checks the request against the Community Plan, and other Metro departments review it too. Nearby owners get an early-notice postcard within 9 days of the filing deadline.
- Post signs and send mailed notice (details below).
- Staff report. Planning posts the draft agenda the Friday before the Commission meeting, with a recommendation of approval, disapproval or approval with conditions.
- Planning Commission public hearing and recommendation.
- Metro Council: first reading introduces the bill, second reading is the public hearing, and third reading is the final vote. Then the Mayor signs or vetoes it.
The property must be current on property taxes before the Council can pass the zone change on second reading. A bill takes effect after the Mayor acts and the Metro Clerk advertises it.
How much does it cost to rezone land in Nashville?
Metro's zone change fee is $2,050. It is listed on the Rezone My Property page (last updated October 26, 2026) and on the zone change application dated September 21, 2026. You pay after Planning sets up the case, by check payable to "Metropolitan Government" or by credit card with a 2.3 percent fee. Surveys, plans and any professional help are extra and depend on the site.
Refunds are limited. Metro considers a written refund request only if little staff time has been spent, and the request has not been publicly noticed, written up in a staff report or presented to the Commission. If a refund is granted, Metro will not accept a substantially similar application from the same owner or applicant for one year.
How long do cases really take? In our 2026 Nashville rezoning data, a separate 2026-only sample of 128 Planning Commission cases (Jan. 8 to Oct. 22, 2026) and their Council bills, the median was 82 days from a case's first Commission agenda to the Council's final vote. The 89.3% approval rate (243 of 272) comes from a different, longer dataset: the 324 cases in our Rezoning Approval Tracker, November 2024 to October 2026.
Metro Nashville rezoning fees (2026)
As published by Metro Planning on its Rezone My Property, Specific Plan and Urban Design Overlay pages. Checked Nov 16, 2026.
| Where | Application | Fee | Source |
|---|---|---|---|
| Nashville and Davidson County | Zone change (base district) | $2,050 | Source |
| Nashville and Davidson County | Zoning text amendment | $4,000 | Source |
| Nashville and Davidson County | SP Tier 1 (0 to 5 units, or under 10,000 sq ft non-residential) | $2,900 | Source |
| Nashville and Davidson County | SP Tier 2 (6 to 25 units, or 10,000 to 25,000 sq ft) | $4,500 | Source |
| Nashville and Davidson County | SP Tier 3 (26 or more units, or over 25,000 sq ft) | $6,100 | Source |
| Nashville and Davidson County | Urban Design Overlay: new, amendment or cancellation | $2,800 | Source |
| Nashville and Davidson County | Zoning letter (PUD, SP or UDO only) | $500 | Source |
When are the 2026 and 2027 filing deadlines?
As of November 16, 2026, the next Planning Commission meeting is December 10, 2026. The October 28, 2026 filing deadline for that meeting has passed. The next filing deadline is December 16, 2026, for the January 28, 2027 meeting, per Metro's adopted 2027 Commission schedule. Metro's 2026 Commission schedule had listed a provisional December 2, 2026 deadline for a January 14, 2027 meeting, with a note that 2027 dates still had to be adopted.
For the December 16, 2026 filing deadline and 2027 meetings, Metro's 2027 Commission schedule says documents must be in the portal 48 hours before the noon fee deadline, and fees are due by noon on the deadline date. The 2026 schedule had used 24 hours. Confirm the current rule with Planning before you file.
Planning Commission filing deadlines are at noon, and Commission meetings start at 4:00 PM in the Sonny West Conference Center, Howard Office Building, 700 President Ronald Reagan Way. Metro says only one Commission meeting will be held in January, July, October, November and December 2026. The Council holds zoning public hearings at its first meeting of each month, except the first meeting in June.
The table follows each filing through Metro's own Council hearing chart, so you can see the dates if a bill moves on the normal schedule. Deferrals push every later date back. Full calendars: 2026 Planning Commission schedule, 2027 Planning Commission schedule, 2026 Council hearing dates and 2027 Council hearing dates.
The 2027 Planning Commission schedule has more deadlines than the chart shows, including January 13, February 10 and March 10, 2027, for meetings on February 25, March 25 and April 22. Metro's chart also notes that Planning will not file any bills for the February 2, 2027 public hearing.
Metro Nashville zone change dates, filing to effective date
From Metro's 2027 Council hearing chart and Planning Commission schedules. Dates assume no deferrals. Checked Nov 16, 2026.
| Filing deadline | Planning Commission | 1st reading | Public hearing | 3rd reading | Effective | Source |
|---|---|---|---|---|---|---|
| Sept. 30, 2026 | Nov. 12, 2026 | Dec. 1, 2026 | Jan. 19, 2027 | Feb. 2, 2027 | Feb. 16, 2027 | Source |
| Oct. 28, 2026 | Dec. 10, 2026 | Feb. 2, 2027 | Mar. 2, 2027 | Mar. 16, 2027 | Apr. 6, 2027 | Source |
| Dec. 16, 2026 | Jan. 28, 2027 | Mar. 2, 2027 | Apr. 6, 2027 | Apr. 20, 2027 | May 4, 2027 | Source |
| Jan. 27, 2027 | Mar. 11, 2027 | Apr. 6, 2027 | May 4, 2027 | May 18, 2027 | June 1, 2027 | Source |
| Mar. 31, 2027 | May 13, 2027 | June 1, 2027 | July 6, 2027 | July 20, 2027 | Aug. 3, 2027 | Source |
| Apr. 28, 2027 | June 10, 2027 | July 6, 2027 | Aug. 3, 2027 | Aug. 17, 2027 | Sept. 7, 2027 | Source |
Where can I see recent Nashville rezoning results?
Our Rezoning Approval Tracker lists every recent Metro Nashville zone change, Specific Plan and Urban Design Overlay case, with the outcome and how long it took. Filter the case table to Nashville, or start with the estimator. Upcoming rezoning hearings lists cases on posted Nashville agendas for the next ~60 days.
Does Metro Council make large rezonings wait 60 days?
No. Under the Council's current Rules of Procedure, amended April 7, 2026, there is no 60-day wait for large rezonings. Rule 29 sets two timing rules for every zoning bill.
A proposal to add a 60-day wait did come up. A Rule 29 amendment filed in November 2025 would have held large-scale zoning bills, meaning 25 or more parcels or 10 or more acres, at least 60 days after first reading, unless every owner signed the application. The Council voted it down on December 4, 2025. Changing a Council rule takes 27 votes, and the amendment got 23, with 13 against.
- Rule 29.1: a zoning bill filed without a Planning Commission recommendation goes to the Commission. The Council cannot hold its public hearing or vote on second reading until the recommendation is filed, or 30 days pass after referral without one.
- Rule 29.2: zoning public hearings are held at the first Council meeting of each month, except the first meeting in June. The Vice Mayor can add hearings at other meetings.
Council rules can change, and any change takes effect 30 days after it passes. Check the current rules before you plan a hearing date.
How are neighbors notified about a Nashville rezoning?
- Signs. You post signs on the property at least 10 calendar days before the Commission meeting, using Planning's directions. If the signs are not posted, the Commission may defer or disapprove the request. Take them down within 3 business days after the last hearing.
- Mailed notice. Metro Code section 17.40.720 requires mailed notice to owners of property within 1,000 feet of a proposed zoning map change. You print the notices on Metro's form with postage, and Planning staff mail them. The Commission's rules require its hearing notice at least 13 days before the hearing.
- Council hearing. For the Council's public hearing, Planning gives you the sign and notice information, and you return the signs and notices to Planning for posting and mailing by Metro staff.
- Email. People and groups who sign up for Planning's e-notices also hear about each request.
- Pending change. A bill filed in October 2026, BL2026-1610, would also mail notice to every dwelling unit within 1,000 feet, so renters and business tenants hear about rezonings too. It passed first reading on October 20, 2026 and would take effect January 1, 2028 if adopted.
Is a community meeting required?
Not for a standard zone change. In a February 2026 staff report, Metro Planning wrote that staff does not typically hold community meetings for rezoning requests, and that the sponsor of the legislation typically facilitates them. In practice, the district councilmember often hosts one.
A meeting is required when the request also needs a major amendment to the Community Plan. Planning staff hold it in the affected area before the public hearing and mail notice to owners within 1,300 feet at least 13 days ahead. If the councilmember confirms a community meeting will be held, the early-notice postcard can be waived.
How do I check a parcel's zoning in Davidson County?
Open Metro's Parcel Viewer. Metro says it shows ownership, zoning and permits and is updated daily. Turn on the Planning layer to see the Community Character policy, which tells you which districts Planning is likely to support.
For an official zoning letter, email planningstaff@nashville.gov with the address, parcel number and a contact email. Planning issues zoning letters only for Planned Unit Developments, Specific Plan districts and Urban Design Overlays, and the fee is $500.
What zoning districts does Metro Nashville use?
Most land owners asking about a rezoning start in an agricultural or single-family district and want one with smaller lots. The table lists Metro's agricultural and residential districts with the minimum lot size Planning publishes for each. The full standards are in Title 17 of the Metro Code.
For rural acreage, see AR2a zoning and what a rezoning to RS or R involves.
Districts ending in -A, such as RS5-A or RM20-A, keep the same uses and density as their companion district, with building placement and design standards for walkable areas. Metro's Zoning Classifications page also lists the mixed-use, office, commercial and industrial districts.
Lot size is only part of the answer. Sewer access, road frontage and the subdivision rules decide how many lots a site can really hold. See subdividing land in Nashville and AR2a and AG rezoning.
Metro Nashville agricultural and residential districts
Minimum lot sizes as published on Metro Planning's Zoning Classifications page. Checked Nov 16, 2026.
| District | Intended for | Minimum lot or density | Source |
|---|---|---|---|
| AG | Agriculture, low density residential | 5 acres | Source |
| AR2a | Agriculture, low density residential | 2 acres | Source |
| RS80 | Single-family | 80,000 sq ft | Source |
| RS40 | Single-family | 40,000 sq ft | Source |
| RS30 | Single-family | 30,000 sq ft | Source |
| RS20 | Single-family | 20,000 sq ft | Source |
| RS15 | Single-family | 15,000 sq ft | Source |
| RS10 | Single-family | 10,000 sq ft | Source |
| RS7.5 | Single-family | 7,500 sq ft | Source |
| RS5 | Single-family | 5,000 sq ft | Source |
| RS3.75 | Single-family | 3,750 sq ft | Source |
| R80 | One- and two-family | 80,000 sq ft | Source |
| R40 | One- and two-family | 40,000 sq ft | Source |
| R30 | One- and two-family | 30,000 sq ft | Source |
| R20 | One- and two-family | 20,000 sq ft | Source |
| R15 | One- and two-family | 15,000 sq ft | Source |
| R10 | One- and two-family | 10,000 sq ft | Source |
| R8 | One- and two-family | 8,000 sq ft | Source |
| R6 | One- and two-family | 6,000 sq ft | Source |
| RM2 to RM100-A | Multifamily | 2 to 100 units per acre, by district | Source |
| MHP | Mobile home park | 2 acres, 9 units per acre | Source |
How is an SP different from a base rezoning, and what is a UDO?
A base rezoning moves land into a standard district such as RS10 or R8, and every use and standard in that district comes with it.
A Specific Plan (SP) district is written for one site. Metro says it is not subject to the standard districts' use and design rules: the design elements are written into the zone change ordinance, which becomes law. An SP still follows the subdivision and stormwater rules. The fee runs from $2,900 to $6,100 by project size, and the Council's rules say an SP bill needs a Planning Commission recommendation before it can be introduced. More on Nashville SP rezoning.
In Nashville, UDO means Urban Design Overlay, not a unified development ordinance. A UDO adds design standards, such as building placement, height, parking and landscaping, on top of the base zoning in a set area. Metro says overlays do not change the uses allowed. Because it is a zone change, a UDO request follows the same process, and the fee is $2,800. Metro lists all of its overlays in Chapter 17.36 of the Metro Code.
Our page on SP zoning in Nashville covers the SP fee tiers and selling land for one.
What happens if a Nashville rezoning is denied?
If you would rather not file at all, see sell land in Nashville, TN. We buy Davidson County land as-is or on rezoning terms.
- A disapproval by the Planning Commission is a recommendation, not the end. The bill can still go to the Council, where Council rules require a roll call vote on third reading for zoning matters the Commission disapproved.
- You can ask the Commission to rehear its decision within 45 days after it approves the minutes for that meeting. The request must show changed circumstances or new information.
- If the Council disapproves the bill, Metro Code section 17.40.100 bars a new application for the same or substantially the same change for one year after the Council's last action. The Council can still reinitiate a rezoning bill at any time, and it has passed resolutions allowing early reapplications.
- A different request is not barred. You can apply sooner for a district the land use policy supports, and a pre-application inquiry is the place to test that.
Who do I contact at Metro about a rezoning?
These are the official public contacts Metro lists for zone changes.
- Metro Planning Department: Metro Office Building, 800 President Ronald Reagan Way, 2nd Floor, Nashville, TN 37210.
- Mailing address: P.O. Box 196300, Nashville, TN 37219-6300.
- Phone: 615-862-7190 (Planning Department front counter).
- Email: planningstaff@nashville.gov. For Planning Portal accounts or problems: ePlanPlanning@nashville.gov.
- Filing deadlines and payment by check: Development Services Center, 1st Floor, 800 President Ronald Reagan Way.
- Your district councilmember: Metro Council districts.
Metro posts a scam notice: fraudsters have impersonated planning and zoning agencies to ask for fees. Pay only through the Planning Portal or the front counter.
How does Liberty Acres help with Nashville land that needs rezoning?
Liberty Acres is a family-owned land buyer, and we made about 250 land purchases in the last 12 months. We buy land that needs rezoning, and on rezoning-terms deals we handle the rezoning work, from the councilmember conversation to the Council's third reading.
Ready to sell? See how to sell land in Nashville, TN.
- We can make an offer on the land as it is zoned today.
- For larger parcels with development potential, we can sign terms that allow time for the rezoning. We handle that work and pay for it.
- You keep title until closing, and the price can reflect the added value.
- We're flexible on terms, we can pay back taxes, and we pay all closing costs. No agents and no commissions.
We'll do what makes sense for your situation. Closing can happen in as little as 14 days. Rezoning terms take longer, because closing waits for the approvals.
This is general information, not legal or tax advice. Talk to a local real estate attorney about your situation.
Common questions
How do I rezone residential land to commercial in Davidson County, Tennessee?
To rezone residential land to commercial in Davidson County, first check that the community plan policy for the area supports commercial use. Then meet with Metro Planning staff and file a zone change or Specific Plan application with the fee and a survey. The Planning Commission recommends after a public hearing, and Metro Council decides after three readings. A base zone change application costs $2,050 (Metro Planning). Metro Nashville approved 89.3% of rezonings with a final result (243 of 272, from 324 cases on Planning Commission agendas, November 2024 to October 2026), with a median of 82 days from the Planning Commission to the final Council vote, per the Liberty Acres Rezoning Approval Tracker.
How do you rezone land in Davidson County?
File a zone change with Metro Planning online and tell your district councilmember first. The fee is $2,050. The Planning Commission holds a hearing and recommends, then the Metro Council decides over three readings, with a public hearing on the second. Metro says it takes 3 to 6 months without complications. The next filing deadline is December 16, 2026, for the January 28, 2027 Commission meeting.
How much does it cost to rezone land in Nashville?
Metro's zone change fee is $2,050. A Specific Plan costs $2,900 to $6,100 by project size, and an Urban Design Overlay costs $2,800. Surveys, plans and professional help are extra.
How long does a rezoning take in Davidson County?
Metro says 3 to 6 months if there are no complications. On Metro's chart, a request filed September 30, 2026 reaches the Planning Commission November 12, 2026 and takes effect February 16, 2027 if nothing is deferred.
Do I have to talk to my councilmember before filing?
Yes. Metro's zone change application says you must contact the district councilmember before you submit it, and you attach a copy of the email you sent to the councilmember and the Metro Council Office.
Is a pre-application meeting required in Nashville?
No. Metro recommends a pre-application inquiry but says it is not mandatory. Email the form to planningstaff@nashville.gov, and a planner typically responds within a week.
Who gets notice of a Nashville rezoning?
Owners of property within 1,000 feet get mailed notice, and you post signs on the property at least 10 days before the Planning Commission meeting. People signed up for Planning's e-notices hear about it too.
Can the Metro Council approve a rezoning the Planning Commission disapproved?
Yes. The Commission's vote is a recommendation and the Council makes the final decision. Council rules require a roll call vote on third reading for zoning matters the Commission disapproved.
How soon can I reapply after the Council denies a rezoning?
Metro Code section 17.40.100 bars an application for the same or substantially the same change for one year after the Council's last action. The Council can reinitiate a bill or authorize an earlier reapplication by resolution.
Rather sell than file the zone change?
We buy Davidson County land as it's zoned today, or on terms where we handle the rezoning and pay for it. More on selling land before it's rezoned.
Closing can happen in as little as 14 days.
Send us your parcelSources
- Metro Planning: Rezone My Property (updated Oct. 26, 2026)
- Metro Planning: Zone Change Application (Sept. 21, 2026)
- Metro Planning: Pre-Application Inquiry Form (Feb. 23, 2026)
- Metro Planning: The Rezoning Process in Nashville (flowchart)
- Rules and Procedures of the Metropolitan Planning Commission (amended Oct. 23, 2025)
- Metro Council Rules of Procedure 2023-2027
- Metro Planning Commission staff report, Feb. 26, 2026
- Planning Commission filing deadlines and meetings, 2026
- Metro Planning Commission filing deadlines and meetings, 2027
- Council public hearing dates for zone changes, 2026
- Council public hearing dates for zone changes, 2027
- Metro Planning: Zoning Classifications
- Metro Planning: Specific Plan Districts
- Metro Planning: Urban Design Overlay
- Metro Planning: Overlays
- Metro Planning: Applications and Fees (refund policy)
- Metro Planning: Meeting Information
- Metro Parcel Viewer
- Metro Council districts
- Ordinance BL2004-121 (1,000-foot notice distance)
- Resolution RS2017-759 (Section 17.40.100 reapplication)
- BL2026-1610, proposed notice to all dwelling units
- Metro Council Rules of Procedure 2023-2027, amended April 7, 2026
- Metro Council Legistar: Rule 29 amendment (failed December 4, 2025)
- Nashville Banner: Metro Council vote on the Rule 29 change (December 5, 2025)
- Metro Planning Commission filing deadlines and meetings, 2026