How to rezone land in Huntsville and Madison County, Alabama

To rezone land in Huntsville, you file the City's rezoning application with the Planning Division, the Zoning Committee and Planning Commission review it, and the City Council decides after a public hearing. Land outside the city has to be annexed first, because Madison County does not list zoning among the rules it enforces in unincorporated areas.

Video (1:41): How to Rezone Land in Huntsville and Madison County, AL. Watch on YouTube or see our channel.

Land in or near Huntsville that needs rezoning or annexation? Start with how we buy rezoning land.

New: the Rezoning Fee Index compares the published rezoning application fee in 57 Tennessee and Alabama cities and counties, sortable, with the median, the range and a free CSV.

Part of our land entitlements guide: rezoning, subdivision, site plans, variances, use permits, annexation and utility approvals, and how each affects a sale.

Who decides a rezoning in Huntsville?

The City of Huntsville zones land only inside its city limits. The Planning Division's Zoning Office takes the application, and the City says rezoning requests must be approved by the Planning Commission and the City Council.

The Planning Commission has 12 members and two supernumerary members appointed by the Mayor and the City Council, and it works through a Zoning subcommittee and a Subdivision subcommittee. A rezoning goes to the Zoning Committee first, then to the full Commission for a recommendation. The City Council makes the final decision after a public hearing. The application says the Council may rezone the land to any suitable district, which may be other than the one you asked for.

Upcoming hearings near you

Own land near a rezoning? Here is what it can mean: a posted hearing on a nearby parcel can change traffic, buyer interest, and what similar land trades for, even before any vote. We keep a live list of upcoming rezoning hearings in Nashville and Huntsville pulled from official agendas for the next ~60 days, with links back to each agenda item.

What are the steps to rezone land in Huntsville?

The City's rezoning page and application set out this order.

  • Check eligibility. Call the Zoning Office at 256-427-5100. The City says not all properties are eligible for rezoning.
  • Prepare the application. It needs original signatures (no copies or e-signatures), a copy of the recorded deed, a vicinity map showing the land on the zoning map, a legal description or survey, and an explanation of why the change is justified. An entity or a representative signs with entity documents or a power of attorney.
  • Turn it in by the monthly date with the filing fee. Late or incomplete requests move to the next month.
  • Sign the Rezoning Application Certification before the Zoning Committee meeting.
  • Zoning Committee review, then the Planning Commission's recommendation.
  • Newspaper notice. The amending ordinance must be published once a week for two consecutive weeks, at least 15 days before the Council passes it, or advertised another way state law allows.
  • City Council public hearing and vote. Once the amendment is published, the City updates the zoning map the next day.

The City's rezoning page does not list a pre-application meeting or a community meeting among the steps. The first step it lists is the eligibility check with Planning staff.

How much does it cost to rezone land in Huntsville?

The City's rezoning application sets the filing fee by acreage. The fee is not refunded, and paying it does not guarantee the change. The form is marked Rev. 8/16 and is still the one linked from the City's rezoning page as of November 2, 2026, so confirm the fee with the Zoning Office before you file. Surveys, legal descriptions and site plans are extra.

City of Huntsville rezoning fees

From the City rezoning application (Rev. 8/16), the form linked from the rezoning page. Non-refundable. Checked Nov 9, 2026.

WhereApplicationFeeSource
City of Huntsville0 to 5 acres$500Source
City of Huntsville5.1 to 10 acres$600Source
City of Huntsville10.1 to 40 acres$700Source
City of HuntsvilleMore than 40 acres$800Source

When are Huntsville's 2026 rezoning deadlines?

Huntsville runs rezonings on one cycle a month. The Zoning Committee meets at 7:30 a.m. and the Planning Commission at 5:00 p.m., normally on the 4th Tuesday in the 2nd floor Chamber at City Hall. On the 2026 calendar the Commission meets three to four weeks after each turn-in date. The schedule also lists the Council's regular meetings each month, but a request reaches the Council only after the Commission acts, so ask Planning staff which Council meeting yours will be on.

See the 2026 rezoning and PUD calendar. A 2027 rezoning calendar was not posted on the City's Planning Commission page when we checked on November 2, 2026.

How long does it take after the Commission? In our Huntsville rezoning data, built from 49 Planning Commission cases from November 2024 to October 2026, the 45 approved cases took a median of 58 days from the Commission meeting to the Council's final vote.

Huntsville 2026 rezoning and PUD calendar

From the City's 2026 schedule. Council dates are the Council's regular meetings that month, not necessarily your hearing; November and December Council dates are adjusted for holidays and subject to change. Checked Nov 9, 2026.

CycleTurn-inZoning CommitteePlanning CommissionCity Council meetingsSource
JanuaryJan. 6Jan. 14Jan. 27Jan. 8 and 29Source
FebruaryFeb. 3Feb. 11Feb. 24Feb. 12 and 26Source
MarchMar. 3Mar. 11Mar. 24Mar. 12 and 26Source
AprilMar. 31Apr. 8Apr. 28Apr. 9 and 23Source
MayMay 5May 13May 26May 14 and 28Source
JuneJune 2June 10June 23June 11 and 25Source
JulyJune 30July 8July 28July 9 and 23Source
AugustAug. 4Aug. 12Aug. 25Aug. 13 and 27Source
SeptemberSept. 1Sept. 9Sept. 22Sept. 10 and 24Source
OctoberOct. 6Oct. 14Oct. 27Oct. 8 and 22Source
NovemberOct. 26Nov. 4Nov. 17Nov. 5 and 19 (adjusted for holidays)Source
DecemberNov. 24Dec. 2Dec. 15Dec. 3 and 17 (adjusted for holidays)Source

How are neighbors notified about a Huntsville rezoning?

The Zoning Ordinance requires the amending ordinance to be published in a newspaper once a week for two consecutive weeks, at least 15 days before the Council passes it. The Council then holds its public hearing. The City's rezoning page does not list any sign or mailed notice that the applicant must handle, so ask the Planning Division what your request needs.

How do I check a parcel's zoning in Huntsville?

Use the City's Zoning Districts map. It shows zoning inside the city limits only. The City's GIS Office is on the 4th floor of City Hall, phone 256-427-5192.

If the land is outside the city, the map will not show a district. Madison County's GIS page directs parcel questions to the Madison County Tax Assessor.

What are Huntsville's zoning districts and minimum lot sizes?

The Zoning Ordinance (updated to April 1, 2026) has no agricultural district. Residence 1 allows single-family homes and agricultural uses, as long as no sales are made on the premises. The table lists the minimum lot areas the ordinance sets for its residential districts and for the districts that set one by acreage.

Residence 1-C and 2-C fit older neighborhoods and mill villages. The ordinance says they are not meant for new subdivisions. The ordinance also has commercial districts C-1 to C-6, a Central Business district, light and heavy industry districts, research park districts and overlays for flood hazard areas, airport noise and slope development.

Huntsville minimum lot sizes by district

From the Huntsville Zoning Ordinance, updated to April 1, 2026. Checked Nov 9, 2026.

DistrictMinimum lot areaMinimum lot widthSource
Residence 115,000 sq ft100 ftSource
Residence 1-A12,000 sq ft75 ftSource
Residence 1-B7,500 sq ft60 ftSource
Residence 1-C5,500 sq ft40 ftSource
Residence 26,000 sq ft single-family; 7,500 sq ft two-family50 ft single-familySource
Residence 2-A8,000 sq ft for the first two units, plus 3,000 per added unit (multifamily)Not set in this tableSource
Residence 2-B6,000 sq ft for the first two units, plus 2,000 per added unit (multifamily)Not set in this tableSource
Residence 2-C4,800 sq ft for newly created lots35 ftSource
PD-H (Planned Development-Housing)Density set in the ordinance creating the districtSet by the ordinanceSource
Office15,000 sq ftNot set in this tableSource
Research Park Commercial1/2 acreNot set in this tableSource
Industrial Park2 acresNot set in this tableSource
Planned Industrial4 acresNot set in this tableSource
Research Park West4 acresNot set in this tableSource
C-5 Commercial Recreation5 acres per useNot set in this tableSource
Heavy Manufacturing10 acresNot set in this tableSource

What happens if a Huntsville rezoning is denied?

The fee is not refunded. Article 90 of the Zoning Ordinance, which covers amendments, does not set a waiting period before you can file again, so ask the Planning Division before you refile the same request. The Council can also approve a different district than the one you asked for, which may be a path when the original request does not fit.

What about land in unincorporated Madison County?

Madison County's Public Works Department answers zoning questions with a letter (updated August 12, 2025) that lists the rules the county enforces in unincorporated areas: the Madison County Subdivision Regulations, the building codes adopted by the County Commission, and the Flood Damage Prevention Ordinance. Zoning is not on that list. Public Works enforces the subdivision regulations, and plat applications are dropped off at its Engineering Department.

To get city zoning, land has to be annexed. Alabama law gives cities the power to zone land inside their corporate limits. Huntsville can annex land that touches the city limits, and the City says it mainly does this when the owners of all the land petition for it. There is no fee to annex. The Council considers the annexation ordinance, and it takes effect when it is published.

Newly annexed land that was never zoned gets its district through its own Council ordinance after a Planning Commission recommendation. In October 2026, for example, the Council zoned 536.68 newly annexed acres in east Huntsville, known as Cleary Farm, to Residence 1 and Residence 2.

A city planning commission may also regulate subdivisions within a mile and a half of its limits (three miles where a local law extends it). Other cities in Madison County run their own zoning; see rezoning land in Madison, AL.

Who do I contact about a Huntsville rezoning?

These are the official public contacts the City and County list.

  • City of Huntsville Planning Division, Zoning Office: Huntsville City Hall, 4th Floor, 305 Fountain Circle, Huntsville, AL 35801. Phone 256-427-5100. Monday to Friday, 8 a.m. to 5 p.m.
  • Mailing address on the rezoning application: P.O. Box 308, Huntsville, AL 35804.
  • City GIS Office: 256-427-5192, City Hall, 4th Floor.
  • Zoning Enforcement Office: 256-564-8008.
  • Madison County Public Works (unincorporated land): 266-C Shields Road, Huntsville, AL 35811. Phone (256) 746-2900. Monday to Friday, 7:00 a.m. to 3:30 p.m.

The City's Planning pages do not list a general department email, so call the Zoning Office. The City warns that official City emails come from an @huntsvilleal.gov address.

Who buys Huntsville land that needs rezoning?

Homebuilders and developers buy land they can build on. For land that needs a rezoning or an annexation first, a buyer will often either price it at today's zoning or sign a contract that gives them time to get the approvals before closing. The approval is not certain, because the Council decides and may pick a different district.

Need to sell on a deadline? Read how to sell land fast, then sell land in Huntsville, AL.

How does Liberty Acres help with Huntsville land that needs rezoning?

Liberty Acres is a family-owned land buyer, and we made about 250 land purchases in the last 12 months. We buy land that needs rezoning or annexation, and on rezoning-terms deals we handle the work with the Zoning Office, the Planning Commission and the City Council.

Ready to sell? See how to sell land in Huntsville, AL.

  • We can make an offer on the land as it is zoned today.
  • For larger parcels with development potential around Huntsville, we can sign terms that allow time for the rezoning or annexation. We handle that work and pay for it.
  • You keep title until closing. Closing comes later, and the price can reflect the added value.
  • We're flexible on terms, we can pay back taxes, and we pay all closing costs. No agents and no commissions.

We'll do what makes sense for your situation. Closing can happen in as little as 14 days. Rezoning terms take longer, because closing waits for the approvals.

This is general information, not legal or tax advice. Talk to a local real estate attorney about your situation.

Common questions

What does each Huntsville zoning district allow, and can my parcel be rezoned to commercial?

Huntsville's Zoning Ordinance has residence districts from Residence 1 to Residence 2-C, commercial districts C-1 to C-6, a Central Business district, light and heavy industry districts and research park districts, but no agricultural district. A parcel moves to a commercial district only by City Council ordinance after a Planning Commission recommendation, and not every property is eligible. Huntsville approved 97.8% of rezoning requests with a final result (45 of 46), with a median of 58 days to the final Council vote, per the Liberty Acres Rezoning Approval Tracker. Districts are listed in the Huntsville Zoning Ordinance.

How do I rezone my land in Huntsville, Alabama, and how long does it take?

To rezone land in Huntsville, confirm with the Planning Division that the parcel is eligible, file the City's rezoning application with the $500 to $800 fee, then go through Planning Commission review and a City Council public hearing and vote. In our data, the median approved case took 58 days from the Commission meeting to the final vote. Huntsville approved 97.8% of rezoning requests with a final result (45 of 46), per the Liberty Acres Rezoning Approval Tracker. The fee is set by acreage on the City of Huntsville Rezoning Application.

How do you rezone land in Huntsville, AL?

File the City's rezoning application with the Planning Division after staff confirm the land is eligible. The fee is $500 to $800 by acreage. The Zoning Committee and Planning Commission review it, and the City Council decides after a public hearing. Filings run monthly, about three to four weeks from turn-in to the Commission.

Who buys land near Huntsville that needs annexation?

Liberty Acres buys land outside the Huntsville city limits that would need annexation, as well as land inside the city that needs rezoning. On larger parcels we can sign terms that allow time for the annexation, and we handle and pay for that work.

Who approves a rezoning in Huntsville?

The City Council, after the Zoning Committee and the Planning Commission review the request. The City says rezoning requests must be approved by the Planning Commission and the City Council.

How much does it cost to rezone land in Huntsville?

The City's application lists non-refundable fees of $500 for up to 5 acres, $600 for 5.1 to 10 acres, $700 for 10.1 to 40 acres and $800 for more than 40 acres. The form is dated 2016, so confirm with the Zoning Office at 256-427-5100.

How long does a Huntsville rezoning take?

The City does not publish a total timeline. Requests run on a monthly cycle: on the 2026 calendar the Planning Commission meets three to four weeks after each turn-in date, and the Council takes the request up after the Commission acts. Late or incomplete requests move to the next month.

How do I find my property's zoning in Huntsville?

Use the City's Zoning Districts map at maps.huntsvilleal.gov/zoningdistricts, or call the GIS Office at 256-427-5192. The map covers land inside the city limits only.

Does unincorporated Madison County have zoning?

Madison County's Public Works letter lists the Subdivision Regulations, the County Commission's building codes and the Flood Damage Prevention Ordinance as the rules it enforces in unincorporated areas. Zoning is not on that list. For city zoning, the land must be annexed.

Can I reapply after Huntsville denies a rezoning?

The Zoning Ordinance's amendment article does not set a waiting period, and the fee is not refunded. Ask the Planning Division before you refile the same request.

Can the City Council rezone my land to a different district than I asked for?

Yes. Huntsville's rezoning application says the request lets the Council rezone the property to any suitable district, which may be other than the one requested.

Have Huntsville land that could be worth more with new zoning?